GAO Reports by subject "Schedule slippages"

Full-text search of 52,072 reports from the Government Accountability Office
From To
Reset

Search Results:

Date Report No. Title
Date Feb. 28, 2001 Report No. GAO-01-284 Title

Nuclear Cleanup: Progress Made at Rocky Flats, but Closure by 2006 Is Unlikely, and Costs May Increase

GAO February 2001 Report to Congressional Committees NUCLEAR CLEANUP Progress Made at Rocky Flats, but Closure by 2006 Is Unlikely, and Costs May Increase GAO-01-284 Contents Letter Appendix I Comments From the Department of Energy 1 42 Appendix II Comments From Kaiser-Hill Company, L.L.C. 44 Appendix III GAO Contacts and Staff Acknowledgments 46 Tables Table 1: Status of Major Cleanup Activities,...
Date Feb. 28, 2001 Report No. GAO-01-6 Title

Defense Acquisitions: Space-Based Infrared System-low at Risk of Missing Initial Deployment Date

United States General Accounting Office GAO February 2001 Report to the Chairman, Subcommittee on Defense, Committee on Appropriations, House of Representatives DEFENSE ACQUISITIONS Space-Based Infrared System-low at Risk of Missing Initial Deployment Date GAO-01-6 Contents Letter Appendixes Appendix I: Space-Based Infrared System-low Program History 3 24 29 30 33 8 13 Appendix II: Technology Read...
Date Nov. 9, 2000 Report No. GAO-01-174R Title

Mass Transit: Review of the South Boston Piers Transitway Finance Plan

United States General Accounting Office Washington, DC 20548 November 9, 2000 The Honorable Richard C. Shelby Chairman The Honorable Frank Lautenberg Ranking Minority Member Subcommittee on Transportation Committee on Appropriations United States Senate The Honorable Frank R. Wolf Chairman The Honorable Martin Sabo Ranking Minority Member Subcommittee on Transportation and Related Agencies Committ...
Date Sept. 15, 2000 Report No. RCED-00-221 Title

Mass Transit: Project Management Oversight Benefits and Future Funding Requirements

United States General Accounting Office GAO September 2000 Report to Congressional Requesters MASS TRANSIT Project Management Oversight Benefits and Future Funding Requirements GAO/RCED-00-221 United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic Development Division B-284186 September 15, 2000 The Honorable Phil Gramm Chairman Committee on Banking, Hous...
Date Aug. 8, 2000 Report No. RCED-00-141 Title

National Ignition Facility: Management and Oversight Failures Caused Major Cost Overruns and Schedule Delays

United States General Accounting Office GAO August 2000 Report to the Committee on Science, House of Representatives NATIONAL IGNITION FACILITY Management and Oversight Failures Caused Major Cost Overruns and Schedule Delays GAO/RCED-00-141 Contents Letter Appendixes Appendix I: Scope and Methodology 3 36 37 45 10 8 22 Appendix II: Comments From the Department of Energy Appendix III: GAO Contacts ...
Date Aug. 8, 2000 Report No. RCED-00-271 Title

National Ignition Facility: Management and Oversight Failures Caused Major Cost Overruns and Schedule Delays

United States General Accounting Office GAO August 2000 Report to the Subcommittee on Military Procurement, Committee on Armed Services, House of Representatives NATIONAL IGNITION FACILITY Management and Oversight Failures Caused Major Cost Overruns and Schedule Delays GAO/RCED-00-271 Contents Letter Appendixes Appendix I: Scope and Methodology 3 36 37 45 10 8 22 Appendix II: Comments From the Dep...
Date July 28, 2000 Report No. NSIAD-00-182 Title

Defense Acquisitions: Howitzer Program Experiencing Cost Increases and Schedule Delays

United States General Accounting Office GAO July 2000 Report to Congressional Requesters DEFENSE ACQUISITIONS Howitzer Program Experiencing Cost Increases and Schedule Delays GAO/NSIAD-00-182 Contents Letter Appendixes Appendix I: Lightweight Howitzer Fiscal Year 2001 Budget Request 3 24 27 8 9 Appendix II: Comments From the Department of Defense Tables Table 1: Key Program Events Table 2: Changes...
Date June 29, 2000 Report No. T-RCED-00-229 Title

National Airspace System: Problems Plaguing the Wide Area Augmentation System and FAA's Actions to Address Them

United States General Accounting Office GAO For Release on Delivery Expected at 9:30 a.m. EDT Thursday June 29, 2000 Testimony Before the Subcommittee on Aviation, Committee on Transportation and Infrastructure, House of Representatives NATIONAL AIRSPACE SYSTEM Problems Plaguing the Wide Area Augmentation System and FAA’s Actions to Address Them Statement of Gerald L. Dillingham Associate Direct...
Date June 22, 2000 Report No. T-RCED-00-215 Title

Nuclear Waste: Observations on DOE's Privatization Initiative for Complex Cleanup Projects

United States General Accounting Office GAO For Release on Delivery Expected at 10:00 am EDT Thursday June 22, 2000 Testimony Before the Subcommittee on Oversight and Investigations, Committee on Commerce, House of Representatives NUCLEAR WASTE Observations on DOE’s Privatization Initiative for Complex Cleanup Projects Statement of Ms. Gary L. Jones, Associate Director, Energy, Resources, and Sc...
Date May 31, 2000 Report No. NSIAD-00-131 Title

Missile Defense: Status of the National Missile Defense Program

United States General Accounting Office GAO May 2000 Report to the Ranking Member Subcommittee on International Security, Proliferation, and Federal Services Committee on Governmental Affairs U. S. Senate MISSILE DEFENSE Status of the National Missile Defense Program GAO/NSIAD-00-131 United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division...
Date April 28, 2000 Report No. RCED-00-106 Title

Nuclear Waste: DOE's Advanced Mixed Waste Treatment Project--Uncertainties May Affect Performance, Schedule, and Price

United States General Accounting Office GAO April 2000 Report to the Chairman, Committee on Commerce, House of Representatives NUCLEAR WASTE DOE’s Advanced Mixed Waste Treatment Project— Uncertainties May Affect Performance, Schedule, and Price GAO/RCED-00-106 Contents Letter Appendixes Tables Appendix I: Comments From the Department of Energy 3 28 Table 1: Original Proposed Treatment Process ...
Date April 26, 2000 Report No. NSIAD-00-75 Title

Defense Acquisitions: Need to Revise Acquisition Strategy to Reduce Risk for Joint Air-to-Surface Standoff Missile

United States General Accounting Office GAO April 2000 Report to the Chairman, Subcommittee on Defense, Committee on Appropriations, House of Representatives DEFENSE ACQUISITIONS Need to Revise Acquisition Strategy to Reduce Risk for Joint Air-to-Surface Standoff Missile GAO/NSIAD-00-75 United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Divis...
Date March 31, 2000 Report No. RCED-00-95R Title

Mass Transit: Review of the Bay Area Rapid Transit District's Airport Extension Finance Plan

B-284933 March 31.2000 The Honorable Richard C. Shelby Chairman The Honorable Frank Lautenberg Ranking Minority Member Subcommittee on Transportation Committee on Appropriations United States Senate The Honorable Frank R. Wolf Chairman The Honorable Martin Sabo Ranking Minority Member Subcommittee on Transportation and Related Agencies Committee on Appropriations House of Representatives Subject: ...
Date March 9, 2000 Report No. RCED-00-86R Title

Clean Coal Technology: Status of Projects and Sales of Demonstrated Technology

m _Aou Intty * GAO igaity * R"Iability United States General Accounting Office Washington, DC 20548 Resources, Community, and Economic Development Division B-284381 March 9, 2000 The Honorable John R. Kasich Chairman, Committee on the Budget House of Representatives Subject: Clean Coal Technology: Status of Projects and Sales of Demonstrated Technology Dear Mr. Chairman: The Congress established t...
Date March 8, 2000 Report No. NSIAD-00-83 Title

State Department: Overseas Emergency Security Program Progressing, But Costs Are Increasing

United States General Accounting Office GAO March 2000 Report to the Chairman, Committee on Foreign Relations, U.S. Senate STATE DEPARTMENT Overseas Emergency Security Program Progressing, but Costs Are Increasing GAO/NSIAD-00-83 Contents Letter Appendixes Appendix I: Status of State Department Emergency Supplemental Appropriations Funds Appendix II: Emergency Supplemental Unobligated Balances, by...
Date Dec. 17, 1999 Report No. AIMD-00-19 Title

District of Columbia: The District Has Not Adequately Planned for and Managed Its New Personnel and Payroll System

United States General Accounting Office GAO December 1999 Report to the Chairman of the Subcommittee on the District of Columbia, Committee on Appropriations, House of Representatives DISTRICT OF COLUMBIA The District Has Not Adequately Planned for and Managed Its New Personnel and Payroll System GAO/AIMD-00-19 United States General Accounting Office Washington, D.C. 20548 Accounting and Informati...
Date Oct. 27, 1999 Report No. NSIAD-00-15 Title

Defense Acquisitions: Army Purchased Truck Trailers That Cannot be Used as Planned

United States General Accounting Office GAO October 1999 Report to the Honorable Tom Harkin, U.S. Senate DEFENSE ACQUISITIONS Army Purchased Truck Trailers That Cannot Be Used as Planned GAO/NSIAD-00-15 United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division B-283452 October 27, 1999 The Honorable Tom Harkin United States Senate Dear Sena...
Date Sept. 29, 1999 Report No. T-NSIAD-99-243 Title

Space Transportation: Progress of the X-33 Reusable Launch Vehicle Program

United States General Accounting Office GAO For Release Expected at 2:00 p.m. EDT Wednesday, September 29, 1999 Testimony Before the Committee on Science, Subcommittee on Space and Aeronautics, House of Representatives SPACE TRANSPORTATION Progress of the X-33 Reusable Launch Vehicle Program Statement of Allen Li, Associate Director, National Security and International Affairs Division GAO/T-NSIAD...
Date Sept. 20, 1999 Report No. RCED-99-267 Title

Nuclear Waste: DOE's Hanford Spent Nuclear Fuel Storage Project--Cost, Schedule, and Management Issues

United States General Accounting Office GAO September 1999 Report to the Chairman, Committee on Commerce, House of Representatives NUCLEAR WASTE DOE’s Hanford Spent Nuclear Fuel Storage Project—Cost, Schedule, and Management Issues GAO/RCED-99-267 GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic Development Division B-283386 September 20, 19...
Date Aug. 19, 1999 Report No. RCED-99-240 Title

Mass Transit: Status of New Starts Transit Projects With Full Funding Grant Agreements

United States General Accounting Office GAO August 1999 Report to Congressional Requesters MASS TRANSIT Status of New Starts Transit Projects With Full Funding Grant Agreements GAO/RCED-99-240 GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic Development Division B-282805 August 19, 1999 Congressional Requesters Since the early 1970s, the federal...
Date Aug. 17, 1999 Report No. NSIAD-99-175 Title

Space Station: Russian Commitment and Cost Control Problems

United States General Accounting Office GAO August 1999 Report to Congressional Requesters SPACE STATION Russian Commitment and Cost Control Problems GAO/NSIAD-99-175 United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division B-280328 Letter August 17, 1999 The Honorable John McCain Chairman, Committee on Commerce, Science and Transportation...
Date Aug. 11, 1999 Report No. NSIAD-99-176 Title

Space Transportation: Status of the X-33 Reusable Launch Vehicle Program

United States General Accounting Office GAO August 1999 Report to Congressional Requesters SPACE TRANSPORTATION Status of the X-33 Reusable Launch Vehicle Program GAO/NSIAD-99-176 United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division B-281611 Letter August 11, 1999 The Honorable Dana Rohrabacher Chairman The Honorable Bart Gordon Rankin...
Date June 9, 1999 Report No. RCED-99-131 Title

Transportation Infrastructure: Impacts of Utility Relocations on Highway and Bridge Projects

United States General Accounting Office GAO June 1999 Report to Congressional Requesters TRANSPORTATION INFRASTRUCTURE Impacts of Utility Relocations on Highway and Bridge Projects GAO/RCED-99-131 GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic Development Division B-280707 June 9, 1999 The Honorable John H. Chafee Chairman The Honorable Max S....
Date May 26, 1999 Report No. RCED-99-64 Title

Ecosystem Planning: Northwest Forest and Interior Columbia River Basin Plans Demonstrate Improvements in Land-Use Planning

United States General Accounting Office GAO May 1999 Report to Congressional Requesters ECOSYSTEM PLANNING Northwest Forest and Interior Columbia River Basin Plans Demonstrate Improvements in Land-Use Planning GAO/RCED-99-64 GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic Development Division B-281830 May 26, 1999 The Honorable Frank Murkowski ...
Date May 13, 1999 Report No. T-AIMD-99-186 Title

Customs Service Modernization: Actions Initiated to Correct ACE Management and Technical Weaknesses

United States General Accounting Office GAO For Release on Delivery Expected at 10 a.m. Thursday, May 13, 1999 Testimony Before the Committee on Finance, U.S. Senate CUSTOMS SERVICE MODERNIZATION Actions Initiated to Correct ACE Management and Technical Weaknesses Statement of Randolph C. Hite Associate Director, Governmentwide and Defense Information Systems Accounting and Information Management ...
Date April 30, 1999 Report No. RCED-99-69 Title

Nuclear Waste: Process to Remove Radioactive Waste From Savannah River Tanks Fails to Work

United States General Accounting Office GAO April 1999 Report to the Ranking Minority Member, Committee on Commerce, House of Representatives NUCLEAR WASTE Process to Remove Radioactive Waste From Savannah River Tanks Fails to Work GAO/RCED-99-69 GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic Development Division B-281907 Le er t Letter April ...
Date April 19, 1999 Report No. T-AIMD-99-149 Title

Year 2000 Computing Crisis: Readiness Improving But Much Work Remains to Ensure Delivery of Critical Services

GAO For Release on Delivery Expected at 9 a.m. Monday, April 19, 1999 United States General Accounting Office Testimony Before the Committee on Government Reform, House of Representatives YEAR 2000 COMPUTING CRISIS Readiness Improving But Much Work Remains to Ensure Delivery of Critical Services Statement of Joel C. Willemssen Director, Civil Agencies Information Systems Accounting and Information...
Date April 14, 1999 Report No. T-AIMD-99-144 Title

Year 2000 Computing Challenge: Federal Government Making Progress But Critical Issues Must Still Be Addressed to Minimize Disruptions

United States General Accounting Office GAO For Release on Delivery Expected at 9:30 a.m. Wednesday, April 14, 1999 Testimony Before the Special Committee on the Year 2000 Technology Problem, U.S. Senate YEAR 2000 COMPUTING CHALLENGE Federal Government Making Progress But Critical Issues Must Still Be Addressed to Minimize Disruptions Statement of Gene L. Dodaro Assistant Comptroller General Accou...
Date April 13, 1999 Report No. NSIAD-99-76 Title

Weapons of Mass Destruction: Effort to Reduce Russian Arsenals May Cost More, Achieve Less Than Planned

United States General Accounting Office GAO April 1999 Report to the Chairman and Ranking Minority Member, Committee on Armed Services, House of Representatives WEAPONS OF MASS DESTRUCTION Effort to Reduce Russian Arsenals May Cost More, Achieve Less Than Planned GAO/NSIAD-99-76 GAO United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division ...
Date March 31, 1999 Report No. NSIAD-99-50 Title

Defense Acquisitions: DOD Efforts to Develop Laser Weapons for Theater Defense

United States General Accounting Office GAO March 1999 Report to Congressional Requesters DEFENSE ACQUISITIONS DOD Efforts to Develop Laser Weapons for Theater Defense GAO/NSIAD-99-50 GAO United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division B-279125 Le er t Le er t Letter March 31, 1999 The Honorable Owen B. Pickett Ranking Minority Me...
Date Feb. 19, 1999 Report No. T-AIMD-99-84 Title

Year 2000 Computing Crisis: The District of Columbia Remains Behind Schedule

GAO For Release on Delivery Expected at 9:30 a.m. Friday, February 19, 1999 United States General Accounting Office Testimony Before the Subcommittee on the District of Columbia, Committee on Government Reform, House of Representatives YEAR 2000 COMPUTING CRISIS The District of Columbia Remains Behind Schedule Statement of Jack L. Brock, Jr. Director, Governmentwide and Defense Information Systems...
Date Jan. 29, 1999 Report No. RCED-99-66R Title

National Airspace System: Observations on American Airlines' 1997 Study of Future Air Traffic Congestion

Resources, Community, Economic Development and Division B-281891 January 29,1999 The Honorable James L. Oberstar Ranking Minority Member Committee on Transportation and Infrastructure House of Representatives Subject: National Airspace Svstem: Observations on American Airlines’ 1997 Studv of Future Air Traffic Conaestion Dear Mr. Oberstar: In 1995, the Federal Aviation Administration (FAA) estim...
Date Jan. 13, 1999 Report No. NSIAD-99-26 Title

Army Medium Trucks: Information on Delivery Delays and Corrosion Problems

United States General Accounting Office GAO January 1999 Report to the Honorable Tom Harkin, U.S. Senate ARMY MEDIUM TRUCKS Information on Delivery Delays and Corrosion Problems GAO/NSIAD-99-26 GAO United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division B-281385 January 13, 1999 The Honorable Tom Harkin United States Senate Dear Senator H...
Date Jan. 1, 1999 Report No. OCG-99-18 Title

Major Management Challenges and Program Risks: National Aeronautics and Space Administration

United States General Accounting Office GAO Performance and Accountability Series January 1999 Major Management Challenges and Program Risks National Aeronautics and Space Administration GAO/OCG-99-18 GAO United States General Accounting Office Washington, D.C. 20548 Comptroller General of the United States January 1999 The President of the Senate The Speaker of the House of Representatives This r...
Date July 10, 1998 Report No. HEHS-98-188R Title

VA Construction: Contract Award Delays

GAO United States General Accounting OfTice Washington, D.C. 20648 Health, Education and Human Services Division B-280287 July 10, 1998 The Honorable Christopher S. Bond Chairman The Honorable Barbara A. MikuLski Ranking Minority Member Subcommittee on VA, HUD, and Independent Agencies Committee on Appropriations United States Senate The Honorable Jerry Lewis Chairman The Honorable Louis Stokes Ra...
Date July 9, 1998 Report No. RCED-98-237R Title

Surface Infrastructure: Review of the Los Angeles County Metropolitan Transportation Authority's Restructuring Plan

d-l Lx A0 United States General Accounting Office Washington, D.C. 20548 Resources, Community, Economic Development and Division B-280462 July 9, 1998 The Honorable Bob Livingston Chairman The Honorable David Obey Ranking Minority Member Committee on Appropriations House of Representatives The Honorable Ted Stevens Chairman The Honorable Robert Byrd Ranking Minority Member Committee on Appropriati...
Date June 24, 1998 Report No. T-NSIAD-98-212 Title

Space Station: U.S. Life-Cycle Funding Requirements

United States General Accounting Office GAO For Release on Delivery Expected at 10:00 a.m., EDT Wednesday, June 24, 1998 Testimony Before the Committee on Science, House of Representatives SPACE STATION U.S. Life-Cycle Funding Requirements Statement of Allen Li, Associate Director, Defense Acquisitions Issues, National Security and International Affairs Division GAO/T-NSIAD-98-212 Mr. Chairman and...
Date May 22, 1998 Report No. NSIAD-98-147 Title

International Space Station: U.S. Life-Cycle Funding Requirements

United States General Accounting Office GAO May 1998 Report to Congressional Requesters INTERNATIONAL SPACE STATION U.S. Life-Cycle Funding Requirements GAO/NSIAD-98-147 GAO United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division B-279653 May 22, 1998 The Honorable John McCain Chairman, Committee on Commerce, Science and Transportation Un...
Date May 12, 1998 Report No. T-RCED-98-119 Title

Nuclear Waste: Management Problems at the Department of Energy's Hanford Spent Fuel Storage Project

United States General Accounting Office GAO For Release on Delivery Expected at 1:00 p.m. EDT Tuesday May 12, 1998 Testimony Before the Subcommittee on Oversight and Investigations, Committee on Commerce, House of Representatives NUCLEAR WASTE Management Problems at the Department of Energy’s Hanford Spent Fuel Storage Project Statement of Gary L. Jones, Associate Director, Energy, Resources, an...
Date March 25, 1998 Report No. T-NSIAD-98-137 Title

F-22 Aircraft: Progress of the Engineering and Manufacturing Development Program

United States General Accounting Office GAO For Release on Delivery Expected at 10:00 a.m., EST Wednesday, March 25, 1998 Testimony Before the Subcommittee on AirLand Forces, Committee on Armed Services, U.S. Senate F-22 AIRCRAFT Progress of the Engineering and Manufacturing Development Program Statement of Louis J. Rodrigues, Director, Defense Acquisition Issues, National Security and Internation...
Date July 30, 1997 Report No. NSIAD-97-196R Title

Multiple Launch Rocket System: Range Less Than Needed and Sustained Rocket Production Not Ensured

GA!!0 United States General Accounting Office Washington, D.C. 20548 National Security and International AfFairs Division B-277394 July 30,’1997 The Honorable Togo D. West, Jr. The Secretary of the Army Subject: Multiple Launch Rocket System: Range Less Than Needed and Sustained Rocket Production Not Ensured Dear Mr. Secretary: During our review of the Multiple Launch Rocket System’ (MARS) s i...
Date June 18, 1997 Report No. T-NSIAD-97-177 Title

Space Station: Cost Control Problems Continue to Worsen

United States General Accounting Office GAO For Release on Delivery Expected at 2:00 a.m., EDT Wednesday, June 18, 1997 Testimony Before the Subcommittee on Science, Technology, and Space, Committee on Commerce, Science, and Transportation, U.S. Senate SPACE STATION Cost Control Problems Continue to Worsen Statement of Thomas J. Schulz, Associate Director, Defense Acquisitions Issues, National Sec...
Date June 16, 1997 Report No. NSIAD-97-150 Title

Strategic Mobility: Late Deliveries of Large, Medium Speed Roll-On/Roll-Off Ships

United States General Accounting Office GAO June 1997 Report to the Secretary of Defense STRATEGIC MOBILITY Late Deliveries of Large, Medium Speed Roll-On/Roll-Off Ships GAO/NSIAD-97-150 GAO United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division B-276849 June 16, 1997 The Honorable William S. Cohen The Secretary of Defense Dear Mr. Secre...
Date March 14, 1997 Report No. RCED-97-63 Title

Department of Energy: Management and Oversight of Cleanup Activities at Fernald

United States General Accounting Office GAO March 1997 Report to Congressional Requesters DEPARTMENT OF ENERGY Management and Oversight of Cleanup Activities at Fernald GAO/RCED-97-63 GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic Development Division B-276108 March 14, 1997 Congressional Requesters Over 50 articles containing allegations of m...
Date March 6, 1997 Report No. T-RCED-97-92 Title

Department of Energy: Improving Management of Major System Acquisitions

United States General Accounting Office GAO For Release on Delivery Expected at 10:00 a.m. EST Thursday March 6, 1997 Testimony Before the Subcommittee on Energy and Environment, Committee on Science, House of Representatives DEPARTMENT OF ENERGY Improving Management of Major System Acquisitions Statement by Victor S. Rezendes, Director, Energy, Resources, and Science Issues, Resources, Community,...
Date March 4, 1997 Report No. RCED-97-85R Title

Department of Energy: Major System Acquisitions From 1980 Through 1996

GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, Economic Development and Division B-276266 March 4, 1997 The Honorable John R. Kasich Chairman, Committee on the Budget House of Representatives Subject: Department of Energv: Maior Svstem Acquisitions From 1980 Through 1996 Dear Mr. Chairman: As requested, we are providing you with a listing of the major syst...
Date Jan. 27, 1997 Report No. NSIAD-97-79R Title

Energy: Longbow Apache Fire Control Radar

GAO United States General Accounting Qffice Washington, D.C. 20548 National Security and International AfTairs Division B-275846 January 27, 1997 The Honorable William S. Cohen The Secretary of Defense Dear Mr. Secretary: During our ongoing review of the Army’ Longbow Apache modification s program located at the U. S. Army’ Aviation and Troop Command, we s developed information that raises con...
Date Dec. 10, 1996 Report No. RCED-97-18 Title

Department of Energy: Contract Reform Is Progressing, but Full Implementation Will Take Years

United States General Accounting Office GAO December 1996 Report to the Chairman, Subcommittee on Energy and Power, Committee on Commerce, House of Representatives DEPARTMENT OF ENERGY Contract Reform Is Progressing, but Full Implementation Will Take Years G A O years 1921 - 1996 GAO/RCED-97-18 GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic De...
Date Nov. 26, 1996 Report No. RCED-97-17 Title

Department of Energy: Opportunity to Improve Management of Major System Acquisitions

United States General Accounting Office GAO November 1996 Report to the Chairman, Committee on Governmental Affairs, U.S. Senate DEPARTMENT OF ENERGY Opportunity to Improve Management of Major System Acquisitions G A O years 1921 - 1996 GAO/RCED-97-17 GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic Development Division B-274876 November 26, 199...
Date Aug. 26, 1996 Report No. NSIAD-96-162 Title

Best Practices: Commercial Quality Assurance Practices Offer Improvements for DOD

United States General Accounting Office GAO August 1996 Report to the Subcommittee on Acquisition and Technology, Committee on Armed Services, U. S. Senate BEST PRACTICES Commercial Quality Assurance Practices Offer Improvements for DOD G A O years 1921 - 1996 GAO/NSIAD-96-162 GAO United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division B-...