Date May 31, 2006 |
Report No. GAO-06-623 |
Title
United States Government Accountability Office GAO
May 2006 Report to Congressional Committees UNITED STATES COAST GUARD Improvements Needed in Management and Oversight of Rescue System Acquisition GAO-06-623 May 2006 UNITED STATES COAST GUARD Highlights
Highlights of GAO-06-623, a report to congressional committees Accountability Integrity Reliability Improvements Needed in Management and Oversig... |
Date May 24, 2006 |
Report No. GAO-06-803T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:00 a.m. EDT Wednesday, May 24, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Status of Projects’s Schedule and Cost As of May 24, 2006
Statement of Terrell Dorn, Director Bernard L. Ungar, Director Physical Infrast... |
Date April 27, 2006 |
Report No. GAO-06-665T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:30 a.m. EDT Thursday, April 27, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost as of April 27, 2006
Statement of Terrell Dorn, Director Bernard L. Ungar, Director Physical Infra... |
Date April 14, 2006 |
Report No. GAO-06-368 |
Title
United States Government Accountability Office GAO
April 2006 Report to Congressional Committees DEFENSE ACQUISITIONS Major Weapon Systems Continue to Experience Cost and Schedule Problems under DOD’s Revised Policy GAO-06-368 April 2006 DEFENSE ACQUISITIONS Highlights
Highlights of GAO-06-368, a report to congressional committees Accountability Integrity Reliability Major Weapon Systems Continu... |
Date April 6, 2006 |
Report No. GAO-06-626T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 3:30 p.m. EDT Thursday, April 6, 2006 Testimony before the Subcommittee on Strategic Forces, Senate Committee on Armed Services SPACE ACQUISITIONS Improvements Needed in Space Systems Acquisitions and Keys to Achieving Them
Statement of Cristina T. Chaplain Acting Director, Acquisition and Sourcing Management Te... |
Date April 5, 2006 |
Report No. GAO-06-585T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:00 a.m. EDT Wednesday, April 5, 2006 Testimony Before the Armed Services Committee, House of Representatives DEFENSE ACQUISITIONS Actions Needed to Get Better Results on Weapons Systems Investments
Statement of David M. Walker Comptroller General of the United States GAO-06-585T April 5, 2006 DEFENSE ACQUISIT... |
Date March 28, 2006 |
Report No. GAO-06-558T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 9:30 a.m. EST Tuesday, March 28, 2006 Testimony Before the Permanent Subcommittee on Investigations, Committee on Homeland Security and Governmental Affairs, U.S. Senate COMBATING NUCLEAR SMUGGLING Challenges Facing U.S. Efforts to Deploy Radiation Detection Equipment in Other Countries and in the United States
... |
Date March 28, 2006 |
Report No. GAO-06-523T |
Title
GAO
For Release on Delivery Expected at 2:30 p.m. EST Tuesday, March 28, 2006 Testimony before the Subcommittee on AirLand, Committee on Armed Services, U.S. Senate TACTICAL AIRCRAFT Recapitalization Goals Are Not Supported by Knowledge-Based F-22A and JSF Business Cases
Statement of Michael Sullivan, Director Acquisition and Sourcing Management GAO-06-523T March 2006 TACTICAL AIRCRAFT Highlights
... |
Date March 22, 2006 |
Report No. GAO-06-389 |
Title
United States Government Accountability Office GAO
March 2006 Report to Congressional Requesters COMBATING NUCLEAR SMUGGLING DHS Has Made Progress Deploying Radiation Detection Equipment at U.S. Ports-of-Entry, but Concerns Remain GAO-06-389 a March 2006 COMBATING NUCLEAR SMUGGLING Highlights
Highlights of GAO-06-389, a report to congressional requesters Accountability Integrity Reliability DHS Ha... |
Date March 20, 2006 |
Report No. GAO-06-310 |
Title
United States Government Accountability Office GAO
March 2006 Report to the Chairman, Subcommittee on Transportation, Treasury, the Judiciary, HUD, and Related Agencies, Committee on Appropriations, U.S. Senate BUSINESS SYSTEMS MODERNIZATION IRS Needs to Complete Recent Efforts to Develop Policies and Procedures to Guide Requirements Development and Management
This report was reposted to the inter... |
Date March 15, 2006 |
Report No. GAO-06-184 |
Title
United States Government Accountability Office GAO
March 2006 Report to Congressional Requesters FINANCIAL MANAGEMENT SYSTEMS Additional Efforts Needed to Address Key Causes of Modernization Failures GAO-06-184 March 2006 FINANCIAL MANAGEMENT SYSTEMS Highlights
Highlights of GAO-06-184, a report to congressional requesters Accountability Integrity Reliability Additional Efforts Needed to Address K... |
Date March 15, 2006 |
Report No. GAO-06-327 |
Title
United States Government Accountability Office GAO
March 2006 Report to Congressional Committees DEFENSE ACQUISITIONS Missile Defense Agency Fields Initial Capability but Falls Short of Original Goals GAO-06-327 March 2006 DEFENSE ACQUISITIONS Highlights
Highlights of GAO-06-327, a report to congressional committees Accountability Integrity Reliability Missile Defense Agency Fields Initial Capabil... |
Date March 15, 2006 |
Report No. GAO-06-447 |
Title
United States Government Accountability Office GAO
March 2006 Report to the Committee on Armed Services, U.S. Senate UNMANNED AIRCRAFT SYSTEMS New DOD Programs Can Learn from Past Efforts to Craft Better and Less Risky Acquisition Strategies GAO-06-447 March 2006 UNMANNED AIRCRAFT SYSTEMS Highlights
Highlights of GAO-06-447, a report to the Committee on Armed Services, U.S. Senate Accountability I... |
Date March 15, 2006 |
Report No. GAO-06-528T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:30 a.m. EST Wednesday, March 15, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Status of Project’s Schedule and Cost as of March 15, 2006
Statement of Bernard L. Ungar, Director Terrell Dorn Assistant Director Physical Infra... |
Date Feb. 21, 2006 |
Report No. GAO-06-360 |
Title
United States Government Accountability Office GAO
February 2006 Report to Congressional Committees BUSINESS SYSTEMS MODERNIZATION Internal Revenue Service’s Fiscal Year 2006 Expenditure Plan GAO-06-360 a February 2006 BUSINESS SYSTEMS MODERNIZATION Highlights
Highlights of GAO-06-360, a report to congressional committees Accountability Integrity Reliability Internal Revenue Service’s Fiscal Y... |
Date Nov. 16, 2005 |
Report No. GAO-06-249T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:00 a.m. EST Wednesday, November 16, 2005 Testimony Before the Committee on Science, House of Representatives POLAR-ORBITING OPERATIONAL ENVIRONMENTAL SATELLITES Technical Problems, Cost Increases, and Schedule Delays Trigger Need for Difficult Trade-off Decisions
Statement of David A. Powner, Director Informa... |
Date Nov. 16, 2005 |
Report No. GAO-06-251T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 11:00 a.m. EST Wednesday, November 16, 2005 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Schedule and Cost
Statement of Bernard L. Ungar, Director Terrell Dorn, Assistant Director Physical Infrastructure Issues GAO-06-251T ... |
Date Nov. 15, 2005 |
Report No. GAO-06-257T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 2:30 p.m. EST Tuesday, November 15, 2005 Testimony Before the Subcommittee on AirLand, Committee on Armed Services, U.S. Senate DOD ACQUISITION OUTCOMES A Case for Change Statement of Katherine V. Schinasi, Managing Director Acquisition and Sourcing Management GAO-06-257T November 15, 2005 DOD ACQUISITION OUTCOM... |
Date Oct. 18, 2005 |
Report No. GAO-06-180T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:30 a.m. EDT Tuesday, October 18, 2005 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Status of Schedule, Fire Protection, Cost, and Related Issues
Statement of Bernard L. Ungar, Director Terrell Dorn, Assistant Director Physical Inf... |
Date Oct. 14, 2005 |
Report No. GAO-06-154 |
Title
United States Government Accountability Office GAO
October 2005 Report to Congressional Requesters NATIONAL AIRSPACE SYSTEM Transformation will Require Cultural Change, Balanced Funding Priorities, and Use of All Available Management Tools GAO-06-154 a October 2005 NATIONAL AIRSPACE SYSTEM Highlights
Highlights of GAO-06-154, a report to congressional requesters Accountability Integrity Reliabilit... |
Date Sept. 15, 2005 |
Report No. GAO-05-1037T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:30 a.m. EDT Thursday, September 15, 2005 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Schedule Delays Continue; Reassessment Underway
Statement of Bernard L. Ungar, Director Terrell Dorn, Assistant Director Physical Infrastructure... |
Date July 22, 2005 |
Report No. GAO-05-774 |
Title
United States Government Accountability Office GAO
July 2005 Report to Congressional Committees BUSINESS SYSTEMS MODERNIZATION Internal Revenue Service’s Fiscal Year 2005 Expenditure Plan GAO-05-774 a July 2005 BUSINESS SYSTEMS MODERNIZATION Highlights
Highlights of GAO-05-774, a report to congressional committees Accountability Integrity Reliability Internal Revenue Service’s Fiscal Year 2005... |
Date June 30, 2005 |
Report No. GAO-05-673 |
Title
United States Government Accountability Office GAO
June 2005 Report to Congressional Requesters COURTHOUSE CONSTRUCTION Information on Project Cost and Size Changes Would Help to Enhance Oversight GAO-05-673 a June 2005 COURTHOUSE CONSTRUCTION Highlights
Highlights of GAO-05-673, a report to congressional requesters Accountability Integrity Reliability Information on Project Cost and Size Changes ... |
Date June 23, 2005 |
Report No. GAO-05-570R |
Title
Washington, DC 20548 June 23, 2005 The Honorable C.W. Bill Young Chairman, Subcommittee on Defense Committee on Appropriations House of Representatives Subject: Defense Acquisitions: Incentives and Pressures That Drive Problems Affecting Satellite and Related Acquisitions Dear Mr. Chairman: In fiscal year 2006, the Department of Defense (DOD) expects to spend more than $23 billion to develop, acqu... |
Date May 17, 2005 |
Report No. GAO-05-714T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:30 a.m. EDT Tuesday, May 17, 2005 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Priority Attention Needed to Manage Schedules and Contracts
Statement of David M. Walker Comptroller General of the United States GAO-05-714T Mr. Chair... |
Date April 14, 2005 |
Report No. GAO-05-485T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:00 a.m. EDT Thursday, April 14, 2005 Testimony Before the Subcommittee on Aviation, Committee on Transportation and Infrastructure, House of Representatives NATIONAL AIRSPACE SYSTEM Progress and Ongoing Challenges for the Air Traffic Organization
Statement of Gerald L. Dillingham, Director, Civil Aviation Iss... |
Date April 13, 2005 |
Report No. GAO-05-333SP |
Title
United States Government Accountability Office GAO
April 2005 GAO Panel NATIONAL AIRSPACE SYSTEM Experts’ Views on Improving the U.S. Air Traffic Control Modernization Program GAO-05-333SP a April 2005 NATIONAL AIRSPACE SYSTEM Highlights
Highlights of GAO-05-333SP Accountability Integrity Reliability Experts’ Views on Improving the U.S. Air Traffic Control Modernization Program Why GAO Convene... |
Date April 6, 2005 |
Report No. GAO-05-519T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 2:30 p.m. EDT Wednesday, April 6, 2005 Testimony Before the Subcommittee on AirLand, Committee on Armed Services, U.S. Senate TACTICAL AIRCRAFT F/A-22 and JSF Acquisition Plans and Implications for Tactical Aircraft Modernization Statement of Michael Sullivan, Director Acquisition and Sourcing Management Issues ... |
Date March 31, 2005 |
Report No. GAO-05-243 |
Title
United States Government Accountability Office GAO
March 2005 Report to Congressional Committees DEFENSE ACQUISITIONS Status of Ballistic Missile Defense Program in 2004 GAO-05-243 March 2005 DEFENSE ACQUISITIONS Highlights
Highlights of GAO-05-243, a report to Congressional Committees Accountability Integrity Reliability Status of Ballistic Missile Defense Program in 2004 Why GAO Did This Study
S... |
Date March 18, 2005 |
Report No. GAO-05-123 |
Title
United States Government Accountability Office GAO
March 2005 Report to the Committee on Government Reform, House of Representatives DEPARTMENT OF ENERGY Further Actions Are Needed to Strengthen Contract Management for Major Projects GAO-05-123 a March 2005 DEPARTMENT OF ENERGY Further Actions Are Needed to Strengthen Contract Management for Major Projects Highlights of GAO-05-123, a report to the... |
Date March 15, 2005 |
Report No. GAO-05-304 |
Title
United States Government Accountability Office GAO
March 2005 Report to Congressional Committees TACTICAL AIRCRAFT Air Force Still Needs Business Case to Support F/A-22 Quantities and Increased Capabilities GAO-05-304 a March 2005 TACTICAL AIRCRAFT Highlights
Highlights of GAO-05-304, a report to congressional committees Accountability Integrity Reliability Air Force Still Needs Business Case to S... |
Date March 15, 2005 |
Report No. GAO-05-271 |
Title
United States Government Accountability Office GAO
March 2005 Report to Congressional Committees TACTICAL AIRCRAFT Opportunity to Reduce Risks in the Joint Strike Fighter Program with Different Acquisition Strategy GAO-05-271 a March 2005 TACTICAL AIRCRAFT Highlights
Highlights of GAO-05-271, a report to Congressional Committees Accountability Integrity Reliability Opportunity to Reduce Risks in t... |
Date March 14, 2005 |
Report No. GAO-05-267 |
Title
United States Government Accountability Office GAO
March 2005 Report to Congressional Committees INFORMATION TECHNOLOGY Customs Automated Commercial Environment Program Progressing, but Need for Management Improvements Continues GAO-05-267 a March 2005 INFORMATION TECHNOLOGY Highlights
Highlights of GAO-05-267, a report to the Subcommittees on Homeland Security, Senate and House Committees on Appr... |
Date March 3, 2005 |
Report No. GAO-05-390T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 9:00 a.m. EST Thursday, March 3, 2005 Testimony Before the Subcommittee on Tactical Air and Land Forces, Committee on Armed Services, House of Representatives TACTICAL AIRCRAFT Status of the F/A-22 and JSF Acquisition Programs and Implications for Tactical Aircraft Modernization Statement of Michael Sullivan and... |
Date Nov. 17, 2004 |
Report No. GAO-05-11 |
Title
United States Government Accountability Office GAO
November 2004 Report to the Chairman, Subcommittee on Aviation, Committee on Transportation and Infrastructure, House of Representatives AIR TRAFFIC CONTROL FAA Needs to Ensure Better Coordination When Approving Air Traffic Control Systems GAO-05-11 a November 2004 AIR TRAFFIC CONTROL FAA Needs to Ensure Better Coordination When Approving Air Traf... |
Date Nov. 17, 2004 |
Report No. GAO-05-46 |
Title
United States Government Accountability Office GAO
November 2004 Report to Congressional Committees BUSINESS SYSTEMS MODERNIZATION IRS’s Fiscal Year 2004 Expenditure Plan GAO-05-46 a November 2004 BUSINESS SYSTEMS MODERNIZATION Highlights
Highlights of GAO-05-46, a report to congressional committees Accountability Integrity Reliability IRS’s Fiscal Year 2004 Expenditure Plan Why GAO Did This S... |
Date Sept. 30, 2004 |
Report No. GAO-04-1054 |
Title
United States Government Accountability Office GAO
September 2004 Report to the Subcommittee on Environment, Technology, and Standards, Committee on Science, House of Representatives POLAR-ORBITING ENVIRONMENTAL SATELLITES Information on Program Cost and Schedule Changes GAO-04-1054 a September 2004 POLAR-ORBITING ENVIRONMENTAL SATELLITES
Highlights of GAO-04-1054, a report to Subcommittee on Envi... |
Date Aug. 20, 2004 |
Report No. GAO-04-822 |
Title
United States Government Accountability Office GAO
August 2004 Report to Congressional Requesters INFORMATION TECHNOLOGY FAA Has Many Investment Management Capabilities in Place, but More Oversight of Operational Systems Is Needed GAO-04-822 a August 2004 INFORMATION TECHNOLOGY FAA Has Many Investment Management Capabilities in Place, but More Oversight of Operational Systems Is Needed Highlights ... |
Date July 21, 2004 |
Report No. GAO-04-915 |
Title
United States Government Accountability Office GAO
July 2004 Report to Congressional Committees MILITARY OPERATIONS Fiscal Year 2004 Costs for the Global War on Terrorism Will Exceed Supplemental, Requiring DOD to Shift Funds from Other Uses
This report was originally issued July 21, 2004. On July 23, 2004, the report on GAO’s Web site was revised to show the correct percentages for Training, Co... |
Date April 23, 2004 |
Report No. GAO-04-409 |
Title
United States General Accounting Office GAO
April 2004 Report to Congressional Committees MISSILE DEFENSE Actions Are Needed to Enhance Testing and Accountability GAO-04-409 a April 2004 MISSILE DEFENSE Actions Are Needed to Enhance Testing and Accountability Highlights of GAO-04-409, a report to congressional committees The Department of Defense (DOD) has treated ballistic missile defense as a pr... |
Date April 1, 2004 |
Report No. GAO-04-457 |
Title
United States General Accounting Office GAO
April 2004 Report to Congressional Committees NUCLEAR WASTE CLEANUP DOE Has Made Some Progress in Cleaning Up the Paducah Site, but Challenges Remain GAO-04-457 a April 2004 NUCLEAR WASTE CLEANUP DOE Has Made Some Progress in Cleaning Up the Paducah Site, but Challenges Remain Highlights of GAO-04-457, a report to congressional committees In 1988, radioa... |
Date Feb. 12, 2004 |
Report No. GAO-04-438T |
Title
United States General Accounting Office GAO
For Release on Delivery Expected at 9:00 a.m. EST Thursday, February 12, 2004 Testimony Before the Subcommittee on Oversight, Committee on Ways and Means, House of Representatives BUSINESS SYSTEMS MODERNIZATION Internal Revenue Service Needs to Further Strengthen Program Management
Statement of Robert F. Dacey Director, Information Security Issues GAO-04... |
Date Nov. 18, 2003 |
Report No. GAO-04-253T |
Title
United States General Accounting Office GAO
For Release on Delivery Expected at 2:00 p.m. EST Tuesday, November 18, 2003 Testimony Before the Subcommittee on Strategic Forces, Committee on Armed Services, U.S. Senate DEFENSE ACQUISITIONS Improvements Needed in Space Systems Acquisition Policy to Optimize Growing Investment in Space
Statement of Robert E. Levin, Director Acquisition and Sourcing Ma... |
Date Oct. 30, 2003 |
Report No. GAO-04-227T |
Title
United States General Accounting Office GAO
For Release on Delivery Expected at 10:00 a.m. EST Thursday, October 30, 2003 Testimony Before the Subcommittee on Aviation, Committee on Transportation and Infrastructure, House of Representatives AIR TRAFFIC CONTROL FAA’s Modernization Efforts—Past, Present, and Future
Statement of Gerald L. Dillingham, Director, Physical Infrastructure Issues GAO-... |
Date Sept. 5, 2003 |
Report No. GAO-03-1031 |
Title
United States General Accounting Office GAO
September 2003 Report to Congressional Committees CHEMICAL WEAPONS Sustained Leadership, Along with Key Strategic Management Tools, Is Needed to Guide DOD’s Destruction Program GAO-03-1031 September 2003 CHEMICAL WEAPONS Sustained Leadership, Along with Key Strategic Management Tools, Is Needed to Guide DOD’s Destruction Program Highlights of GAO-03-... |
Date July 28, 2003 |
Report No. GAO-03-583 |
Title
United States General Accounting Office GAO
July 2003 Report to Congressional Requesters NUCLEAR WEAPONS Opportunities Exist to Improve the Budgeting, Cost Accounting, and Management Associated with the Stockpile Life Extension Program GAO-03-583 a July 2003 NUCLEAR WEAPONS Opportunities Exist to Improve the Budgeting, Cost Accounting, and Management Associated with the Stockpile Life Extension Pr... |
Date Sept. 24, 2002 |
Report No. GAO-02-1069R |
Title
United States General Accounting Office Washington, DC 20548 September 24, 2002 The Honorable Constance A. Morella Chairwoman Subcommittee on the District of Columbia Committee on Government Reform House of Representatives Subject: District of Columbia: Status of Construction of the Convention Center Dear Madam Chairwoman: You asked us to provide periodic briefings on the status of the constructio... |
Date July 24, 2002 |
Report No. GAO-02-898R |
Title
United States General Accounting Office Washington, DC 20548 July 24, 2002 The Honorable Tom Harkin The Honorable Charles E. Grassley The Honorable Peter G. Fitzgerald The Honorable Richard Durbin United States Senate The Honorable Lane Evans The Honorable James A. Leach The Honorable Jim Nussle House of Representatives Subject: 2002 Update of the 155 mm Lightweight Howitzer In July 2000 and April... |
Date Dec. 12, 2001 |
Report No. GAO-02-93R |
Title
United States General Accounting Office Washington, DC 20548 December 12, 2001 The Honorable Mac Thornberry Chairman The Honorable Ellen O. Tauscher Ranking Minority Member Special Oversight Panel on Department of Energy Reorganization Committee on Armed Services House of Representatives Subject: NNSA Management: Progress in the Implementation of Title 32 Title 32 of the National Defense Authoriza... |
Date June 7, 2001 |
Report No. GAO-01-450 |
Title
United States General Accounting Office GAO
June 2001 Report to the Honorable Peter A. DeFazio, House of Representatives DEFENSE ACQUISITION Comanche Program Objectives Need to Be Revised to More Achievable Levels GAO-01-450 Contents Letter
Results in Brief Background The Comanche Program Continues to Experience Cost Increases, Schedule Delays, and Performance Shortfalls The Army Plans to Begin Co... |