B-2 Bomber: Status of Efforts to Acquire 21 Operational Aircraft

  Premium   Download PDF Now (35 pages)
Report Type Reports and Testimonies
Report Date Oct. 22, 1996
Report No. NSIAD-97-11
Subject
Summary:

Seeking to control the cost of its $45 billion B-2 bomber program, the Air Force has scaled back combat testing of the radar-evading aircraft in order to complete all flight tests by July 1997; however, a host of factors still jeopardize the Air Force's ability to complete flight testing on schedule. This is GAO's third report discussing the Air Force's progress in acquiring B-2 aircraft. GAO (1) highlights recent program changes; (2) discusses program funding and current cost estimates; and (3) shows the progress achieved in the flight test program, production, and modification efforts.