Date Report No. Title
Date June 19, 2006 Report No. GAO-06-888T Title

Nuclear Regulatory Commission: Preliminary Observations on Its Process to Oversee the Safe Operation of Nuclear Power Plants

United States Government Accountability Office GAO For Release on Delivery Expected at 4:00 p.m. EDT Monday, June 19, 2006 Testimony Before the Subcommittee on Oversight and Investigations, Committee on Energy and Commerce, U.S. House of Representatives NUCLEAR REGULATORY COMMISSION Preliminary Observations on Its Process to Oversee the Safe Operation of Nuclear Power Plants Statement of Jim Wells...
Date May 26, 2005 Report No. GAO-05-754T Title

Nuclear Regulatory Commission: Challenges Facing NRC in Effectively Carrying Out Its Mission

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EDT Thursday, May 26, 2005 Testimony Before the Subcommittee on Clean Air, Climate Change, and Nuclear Safety, Committee on Environment and Public Works, U.S. Senate NUCLEAR REGULATORY COMMISSION Challenges Facing NRC in Effectively Carrying Out Its Mission Statement of Jim Wells, Director Natural Res...
Date Sept. 14, 2004 Report No. GAO-04-1064T Title

Nuclear Regulatory Commission: Preliminary Observations on Efforts to Improve Security at Nuclear Power Plants

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EDT Tuesday, September 14, 2004 Testimony Before the Subcommittee on National Security, Emerging Threats, and International Relations, Committee on Government Reform, House of Representatives NUCLEAR REGULATORY COMMISSION Preliminary Observations on Efforts to Improve Security at Nuclear Power Plants ...
Date Sept. 4, 2003 Report No. GAO-03-752 Title

Nuclear Regulatory Commission: Oversight of Security at Commercial Nuclear Power Plants Needs to Be Strengthened

United States General Accounting Office GAO September 2003 Report to Congressional Requesters NUCLEAR REGULATORY COMMISSION Oversight of Security at Commercial Nuclear Power Plants Needs to Be Strengthened GAO-03-752 a September 2003 NUCLEAR REGULATORY COMMISSION Highlights of GAO-03-752, a report to congressional requesters Oversight of Security at Commercial Nuclear Power Plants Needs to Be Stre...
Date Oct. 30, 1992 Report No. RCED-93-14 Title

Nuclear Security: Safeguards and Security Planning at DOE Facilities Incomplete

lJxGtml States General Accounting Office GAO Report to the Chairman, Subcornrnittee on Oversight and Investigations, Committee on Energy and Commerce, House of Representatives i NUCLEAR SECURITY Safeguards and Security Planning at DOE Facilities Incomplete 148434 GAO united Statee General Accounting OfXlce Washhgton, D.C. 20648 B-249847 October 30, 1992 The Honorable John D. Dingell Chairman, Subc...
Date Nov. 13, 1987 Report No. RCED-88-8 Title

Nuclear Safety: Reactor Design, Management, and Emergency Preparedness at Fort St. Vrain

_ . (;A0 November1987 United States General Accounting I I Office Reportko &e Honorable Timothy E. Wirth, U.S. Senate NUCLEAR SAFETY Reactor Design, Management,and ~fT!wncY Reparedness at Fort St. Vrain ulul I!111 134670 , ,. ,’ ‘ .’ , lksources, Commutity, and Economic Development Division B-229002 November 13, 1987 The Honorable Timothy E. Wirth United States Senate Dear Senator Wirth: Thi...
Date July 13, 1983 Report No. RCED-83-141 Title

Energy: Additional Improvements Needed in Physical Security at Nuclear Powerplants

. . BY THE U.S.GENERAL ACCOUNTING Report To The Chairman, Nuclear Regulatory Commission OFFICE Additional Improvements Needed In Physical Security At Nuclear Powerplants Since the middle 1970’s, the Nuclear Regulatory Commission and powerplant operators have taken measures to reduce the vulnerability of powerplants to attempted acts of sabotage. GAO’s evaluation disclosed that further improvem...
Date July 20, 1982 Report No. EMD-82-90 Title

Energy: Response to Questions Raised Concerning Three Mile Island-2 Cleanup Schedule and Cost

UNITED STATES GENERAL ACCOUNTING OFFfcE WASHINGTON, D.C. 20548 ENERGY AND MINERALS DtVIS.ON RELEASED The Honorable Morris K. Udall Chairman, Committee on Interior and Insular Affairs House of Representatives The Honorable Manuel Lujan, Jr. Ranking Minority Member Committee on Interior and Insular House of Representatives Subject: Affairs Response to Questions Raised Concerning TMI-2 Cleanup Schedu...
Date March 10, 1981 Report No. EMD-81-60 Title

Financial Management: Tennessee Valley Authority Needs To Improve Security and Inventory Controls at Power Sites

UNITED STATES GENERAL WASHINGTON, ACCOUNTING D.C. 20548 OFFICE ENERGY AND MINERALS DIVISION MARCH lo,1981 B-202341 Mr. S. David Freeman Board of Directors Chairman, Tennessee Valley Authority Dear Mr. Chairman: The Eennessee Valley Authority Security and Inventory Controls (EMD-81-60) Needs to Improve at Power Site3 Subject: During our recent survey of the Tennessee Valley Authority’s one area t...
Date Feb. 19, 1980 Report No. EMD-80-48 Title

Energy: Assessment of Various Aspects of This Nation's Nuclear Safeguards Programs

RESTRICTED ~WM##&#& by the Office - O$ RELEASED H-197546 February 19, 1980 The Honorable John Glenn Chairman, Subcommittee on Energy, Nuclear Proliferation and Federal Services Committee on Governmental Affairs United States Senate Dear Mr. Chairman: Assessment of of this Li;iation's nuclearvarious aspects programs safeguards (EMD-80-48) J llllllllllllllll ll 111965 Subject: Protecting nuclear mat...
Date May 5, 1977 Report No. 101913 Title

Energy: Nuclear Powerplant Security

DCCUMENT SESURE 01913 - ([1312268] Nuclear Powerplant Security. Bay 5, 1977. 10 pp. Testimony before the House Committee on Interior and Insular Affairs: Energy and the Bnvironaent Subcommittee; by Ronte Canfield, Jr., Director, Energy and Minerals Div. Issue hrea: Energy 41600). Contact: Energy and Minerals Div. Budget Function: Natural Resourcec, Environment, and Energy: Energy (305). organizati...
Date April 7, 1977 Report No. EMD-77-32 Title

Energy: Security at Nuclear Power Plants, at Best, Inadequate

DCUMENT FESURE 01908 A1052052] Security at Nuclear owerplants, at Best, Inadequate. ED-77-32; B-127945. April 7, 177. 25 pp. Report to the Congress; by Robert F. Keller, Acting Comptroller General. Issue Area: Energy 1600). Contact: Energy and inerals Div. Budget Functicn: Natural Resources, Environment, and Energy: Energy (305). Organizaticn Concerned: Nuclear Regulatory Ccumission. Congressional...
Date Oct. 16, 1974 Report No. RED-75-283 Title

Energy: Need for Improved Security Programs at Commercial Nuclear Power Plants

The Honorzble Dixy Let chairman , Atoziic Energy Ray Coznissfon j, ,t. 1 i Dear Dr. Ray: the security which warrant systems at coxxercial your attention. nuclear powerplant 39 and We have surveyed have noted issues As you know, security in the nuclear industry has been a mstter of considerable public and congressional concern rr,ostly related to safeguards for preventing the theft of special nucle...