Menu Search Account

LegiStorm

Get LegiStorm App Visit Product Demo Website
» Get LegiStorm App
» Get LegiStorm Pro Free Demo

GAO Reports by subject "NASA International Space Station Alpha Program"

Full-text search of 51,950 reports from the Government Accountability Office
From To
Reset

Search Results:

Date Report No. Title
Date Nov. 27, 2001 Report No. GAO-02-184 Title

NASA: Status of Plans for Achieving Key Outcomes and Addressing Major Management Challenges

United States General Accounting Office GAO November 2001 Report to the Ranking Minority Member, Committee on Governmental Affairs, U.S. Senate NASA Status of Plans for Achieving Key Outcomes and Addressing Major Management Challenges GAO-02-184 Contents Letter Results in Brief Background Assessment of NASA’s Performance Goals and Strategies for Accomplishing Selected Key Outcomes Comparison of ...
Date Sept. 6, 2001 Report No. GAO-01-1122T Title

Space Shuttle Safety: Update on NASA's Progress in Revitalizing the Shuttle Workforce and Making Safety Upgrades

United States General Accounting Office GAO Testimony Before the Subcommittee on Science, Technology and Space, Committee on Commerce, Science, and Transportation, U.S. Senate For Release on Delivery Expected at 2:30 p.m. EDT Thursday September 6, 2001 SPACE SHUTTLE SAFETY Update on NASA's Progress in Revitalizing the Shuttle Workforce and Making Safety Upgrades Statement of Allen Li, Director Acq...
Date Aug. 31, 2001 Report No. GAO-01-1000R Title

NASA: International Space Station and Shuttle Support Cost Limits

United States General Accounting Office Washington, DC 20548 August 31, 2001 The Honorable Ernest Hollings Chairman The Honorable John McCain Ranking Minority Member Committee on Commerce, Science, and Transportation United States Senate The Honorable Sherwood L. Boehlert Chairman The Honorable Ralph Hall Ranking Minority Member Committee on Science House of Representatives Subject: NASA: Internat...
Date June 20, 2001 Report No. GAO-01-633 Title

Space Station: Inadequate Planning and Design Led to Propulsion Module Project Failure

United States General Accounting Office GAO June 2001 Report to Congressional Requesters SPACE STATION Inadequate Planning and Design Led to Propulsion Module Project Failure GAO-01-633 Contents Letter Appendix I Comments From the National Aeronautics and Space Administration 1 15 Appendix II Staff Acknowledgments 17 Figures Figure 1: Diagram of Node X Option 11 Page i GAO-01-633 Space Station Uni...
Date Aug. 15, 2000 Report No. NSIAD/GGD-00-186 Title

Space Shuttle: Human Capital and Safety Upgrade Challenges Require Continued Attention

United States General Accounting Office GAO August 2000 Report to the Chairman, Committee on Commerce, Science, and Transportation, U.S. Senate SPACE SHUTTLE Human Capital and Safety Upgrade Challenges Require Continued Attention GAO/NSIAD/GGD-00-186 Contents Letter Appendixes Appendix I: Space Shuttle Program Skill Shortfall Areas 3 18 19 20 Appendix II: Space Shuttle Upgrades Appendix III: GAO C...
Date April 28, 2000 Report No. NSIAD-00-96R Title

Space Station: Russian-Built and Service Module Compliance With Safety Requirements

B-284687 April 282000 The Honorable F. James Sensenbrenner, Jr. Chairman Committee on Science House of Representatives Subject: Space Station: Russian-Built Zarva and Service Module Compliance With Safe@ Reauirements Dear Mr. Chairman: NASA invited Russia to participate in the International Space Station program in 1993 with the expectation that Russian involvement would reduce the cost, speed up ...
Date March 22, 2000 Report No. T-NSIAD-00-133 Title

Space Shuttle: Human Capital Challenges Require Management Attention

United States General Accounting Office GAO For Release on Delivery Expected at 2:30 p.m., EST Wednesday, March 22, 2000 Testimony Before the Subcommittee on Science, Technology, and Space, Committee on Commerce, Science, and Transportation, U.S. Senate SPACE SHUTTLE Human Capital Challenges Require Management Attention Statement of Allen Li, Associate Director, Defense Acquisitions Issues, Nation...
Date March 16, 2000 Report No. T-NSIAD-00-128 Title

Space Station: Russian Compliance With Safety Requirements

United States General Accounting Office GAO For Release on Delivery Expected at 10:00 a.m. Thursday March 16, 2000 Testimony Before the Subcommittee on Space and Aeronautics, Committee on Science, House of Representatives SPACE STATION Russian Compliance With Safety Requirements Statement of Allen Li, Associate Director, National Security and International Affairs Division GAO/T-NSIAD-00-128 Mr. C...
Date Nov. 3, 1999 Report No. NSIAD-00-14 Title

Export Controls: International Space Station Technology Transfers

United States General Accounting Office GAO November 1999 Report to the Chairman and Ranking Minority Member, Committee on Science House of Representatives EXPORT CONTROLS International Space Station Technology Transfers GAO/NSIAD-00-14 Contents Letter Appendixes Appendix I: Licenses Commodities Exported Using Individual Validated 3 18 19 20 26 Appendix II: Examples of ISS-Related Commodities Expo...
Date Sept. 29, 1999 Report No. T-NSIAD-99-243 Title

Space Transportation: Progress of the X-33 Reusable Launch Vehicle Program

United States General Accounting Office GAO For Release Expected at 2:00 p.m. EDT Wednesday, September 29, 1999 Testimony Before the Committee on Science, Subcommittee on Space and Aeronautics, House of Representatives SPACE TRANSPORTATION Progress of the X-33 Reusable Launch Vehicle Program Statement of Allen Li, Associate Director, National Security and International Affairs Division GAO/T-NSIAD...
Date Aug. 17, 1999 Report No. NSIAD-99-175 Title

Space Station: Russian Commitment and Cost Control Problems

United States General Accounting Office GAO August 1999 Report to Congressional Requesters SPACE STATION Russian Commitment and Cost Control Problems GAO/NSIAD-99-175 United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division B-280328 Letter August 17, 1999 The Honorable John McCain Chairman, Committee on Commerce, Science and Transportation...
Date Aug. 11, 1999 Report No. NSIAD-99-176 Title

Space Transportation: Status of the X-33 Reusable Launch Vehicle Program

United States General Accounting Office GAO August 1999 Report to Congressional Requesters SPACE TRANSPORTATION Status of the X-33 Reusable Launch Vehicle Program GAO/NSIAD-99-176 United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division B-281611 Letter August 11, 1999 The Honorable Dana Rohrabacher Chairman The Honorable Bart Gordon Rankin...
Date April 29, 1999 Report No. T-NSIAD-99-117 Title

Space Station: Status of Russian Involvement and Cost Control Efforts

United States General Accounting Office GAO For Release Expected at 10:00 a.m., EDT on April 29, 1999 Testimony Before the Subcommittee on Science, Technology, and Space, Committee on Commerce, Science, and Transportation, U.S. Senate SPACE STATION Status of Russian Involvement and Cost Control Efforts Statement of Allen Li, Associate Director, National Security and International Affairs Division ...
Date Jan. 1, 1999 Report No. OCG-99-18 Title

Major Management Challenges and Program Risks: National Aeronautics and Space Administration

United States General Accounting Office GAO Performance and Accountability Series January 1999 Major Management Challenges and Program Risks National Aeronautics and Space Administration GAO/OCG-99-18 GAO United States General Accounting Office Washington, D.C. 20548 Comptroller General of the United States January 1999 The President of the Senate The Speaker of the House of Representatives This r...
Date May 22, 1998 Report No. NSIAD-98-147 Title

International Space Station: U.S. Life-Cycle Funding Requirements

United States General Accounting Office GAO May 1998 Report to Congressional Requesters INTERNATIONAL SPACE STATION U.S. Life-Cycle Funding Requirements GAO/NSIAD-98-147 GAO United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division B-279653 May 22, 1998 The Honorable John McCain Chairman, Committee on Commerce, Science and Transportation Un...
Date Dec. 1, 1997 Report No. NSIAD-98-42 Title

Space Surveillance: DOD and NASA Need Consolidated Requirements and a Coordinated Plan

United States General Accounting Office GAO December 1997 Report to Congressional Requesters SPACE SURVEILLANCE DOD and NASA Need Consolidated Requirements and a Coordinated Plan GAO/NSIAD-98-42 GAO United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division B-275848 December 1, 1997 The Honorable Dana Rohrabacher Chairman The Honorable Rober...
Date Oct. 1, 1997 Report No. T-NSIAD-98-21 Title

Space Shuttle: Upgrade Activities and Carryover Balances

United States General Accounting Office GAO For Release on Delivery Expected at 10:00 a.m., EST Wednesday, October 1, 1997 Testimony Before the Subcommittee on Space and Aeronautics, Committee on Science, House of Representatives SPACE SHUTTLE Upgrade Activities and Carryover Balances Statement of Allen Li, Associate Director, Defense Acquisitions Issues, National Security and International Affair...
Date Sept. 18, 1997 Report No. T-NSIAD-97-262 Title

Space Station: Deteriorating Cost and Schedule Performance Under the Prime Contract

United States General Accounting Office GAO For Release on Delivery Expected at 2:00 p.m., EDT Thursday, September 18, 1997 Testimony Before the Subcommittee on Science, Technology, and Space, Committee on Commerce, Science, and Transportation, U.S. Senate SPACE STATION Deteriorating Cost and Schedule Performance Under the Prime Contract Statement of Allen Li, Associate Director, Defense Acquisiti...
Date Sept. 16, 1997 Report No. NSIAD-97-213 Title

Space Station: Cost Control Problems Are Worsening

United States General Accounting Office GAO September 1997 Report to Congressional Requesters SPACE STATION Cost Control Problems Are Worsening GAO/NSIAD-97-213 GAO United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division B-276834 September 16, 1997 The Honorable Dale Bumpers United States Senate The Honorable John Dingell House of Represe...
Date June 18, 1997 Report No. T-NSIAD-97-177 Title

Space Station: Cost Control Problems Continue to Worsen

United States General Accounting Office GAO For Release on Delivery Expected at 2:00 a.m., EDT Wednesday, June 18, 1997 Testimony Before the Subcommittee on Science, Technology, and Space, Committee on Commerce, Science, and Transportation, U.S. Senate SPACE STATION Cost Control Problems Continue to Worsen Statement of Thomas J. Schulz, Associate Director, Defense Acquisitions Issues, National Sec...
Date July 24, 1996 Report No. T-NSIAD-96-210 Title

Space Station: Cost Control Difficulties Continue

United States General Accounting Office GAO For Release on Delivery Expected at 9:30 am, EDT Wednesday, July 24, 1996 Testimony Before the Subcommittee on Science, Technology, and Space, Committee on Commerce, Science and Transportation, United States Senate SPACE STATION Cost Control Difficulties Continue Statement of Thomas J. Schulz, Associate Director, Defense Acquisitions Issues, National Sec...
Date July 17, 1996 Report No. NSIAD-96-135 Title

Space Station: Cost Control Difficulties Continue

United States General Accounting Office GAO July 1996 Report to the Ranking Minority Member, Committee on Commerce House of Representatives SPACE STATION Cost Control Difficulties Continue G A O years 1921 - 1996 GAO/NSIAD-96-135 GAO United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division B-271491 July 17, 1996 The Honorable John D. Dinge...
Date July 28, 1995 Report No. NSIAD-95-171 Title

Space Shuttle: Declining Budget and Tight Schedule Could Jeopardize Space Station Support

United States General Accounting Office GAO July 1995 Report to the Chairman, Subcommittee on Oversight of Government Management and the District of Columbia, Committee on Governmental Affairs, U.S. Senate SPACE SHUTTLE Declining Budget and Tight Schedule Could Jeopardize Space Station Support GAO/NSIAD-95-171 GAO United States General Accounting Office Washington, D.C. 20548 National Security and...
Date June 15, 1995 Report No. NSIAD-95-118 Title

Space Shuttle: NASA Must Reduce Costs Further to Operate Within Future Projected Funds

‘. : - _.._ ,..-II -.- GAO United States General Accounting OIlice Washington, D.C. 20548 ~ . .._ - . ~.~~ National Security and International Affairs Division B-260706 June 15,1995 The Honorable William S. Cohen Chairman, Subcommittee on Oversight of Government Management and the District of Columbia Committee on Governmental Affairs United States Senate The Honorable James A Hayes House of Rep...
Date June 12, 1995 Report No. NSIAD-95-163 Title

Space Station: Estimated Total U.S. Funding Requirements

GAO Report tci CongressionaI Requesters , United States General Accounting Office Washington, D.C. 20548 National Security and International Affairs Division B-261547 June 12,1995 The Honorable Dale Bumpers United States Senate The Honorable Dick Zimmer The Honorable Gerald Solomon House of Representatives As you requested, we have reviewed the current estimated costs of the National Aeronautics a...
Date Nov. 22, 1994 Report No. NSIAD-95-33 Title

Space Station: Plans to Expand Research Community Do Not Match Available Resources

United States General Accounting Office GAO November 1994 Report to the Ranking Minority Member, Subcommittee on Oversight of Government Management, Committee on Governmental Affairs, U.S. Senate SPACE STATION Plans to Expand Research Community Do Not Match Available Resources GAO/NSIAD-95-33 GAO United States General Accounting Office Washington, D.C. 20548 National Security and International Aff...
Date July 29, 1994 Report No. NSIAD-94-248 Title

Space Station: Update on the Impact of the Expanded Russian Role

8atesGenedAccounting Office Utitt?dS Report to the Ranking Minority Member, Subcommittee on Oversight of Government Management, Committee on Governmental Affairs, United States Senate July 1994 SPACE STATION Update on the Impact of the Expanded Russian Role Printed *uAcavEnwENl OFFKS ?Rmwa Tnlazs?u GAO/NSIAD-94-248 copies of tMs document will be available shortly. GAO Form 171 W2/87) , B-257996 i ...
Date June 21, 1994 Report No. NSIAD-94-220 Title

Space Station: Impact of the Expanded Russian Role on Funding and Research

United States General Accounting Office GAO June 1994 Report to the Ranking Minority Member, Subcomtiittee on Oversight of Government Management, Committee on Governmental Affairs, U.S. Senate SPACE STATION Impact of the Expanded Russian Role on Funding md Reseaxeh ’ GAO/NSIAD-94-220 United States General Accounting Office Washington, D.C. 20548 National Security and International AfTairs Divisi...