Date Report No. Title
Date Nov. 16, 2011 Report No. GAO-12-68 Title

Haiti Reconstruction: Factors Contributing to Delays in USAID Infrastructure Construction

GAO November 2011 United States Government Accountability Office Report to Congressional Committees HAITI RECONSTRUCTION Factors Contributing to Delays in USAID Infrastructure Construction GAO-12-68 November 2011 HAITI RECONSTRUCTION Factors Contributing to Delays in USAID Infrastructure Construction Highlights of GAO-12-68, a report to congressional committees Why GAO Did This Study On January 12...
Date Oct. 18, 2011 Report No. GAO-12-102R Title

Government Operations: Prior Experience and Past Performance as Evaluation Criteria in the Award of Federal Construction Contracts

  United States Government Accountability Office   Washington, DC 20548 October 18, 2011 The Honorable Joseph I. Lieberman Chairman Committee on Homeland Security and Governmental Affairs United States Senate The Honorable Jon Tester Committee on Homeland Security and Governmental Affairs United States Senate Subject: Prior Experience and Past Performance as Evaluation Criteria in the Award of F...
Date Sept. 20, 2011 Report No. GAO-11-848 Title

Modernizing the Nuclear Security Enterprise: The National Nuclear Security Administration's Proposed Acquisition Strategy Needs Further Clarification and Assessment

United States Government Accountability Office GAO September 2011 Report to the Subcommittee on Energy and Water Development, Committee on Appropriations, House of Representatives MODERNIZING THE NUCLEAR SECURITY ENTERPRISE The National Nuclear Security Administration’s Proposed Acquisition Strategy Needs Further Clarification and Assessment GAO-11-848 September 2011 MODERNIZING THE NUCLEAR SECU...
Date April 14, 2011 Report No. GAO-11-486T Title

Davis-Bacon Act: Methodological Expertise Critical for Improving Survey Quality

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EDT Thursday, April 14, 2011 Testimony Before the Subcommittee on Workforce Protections, Committee on Education and the Workforce, House of Representatives DAVIS-BACON ACT Methodological Expertise Critical for Improving Survey Quality Statement of Andrew Sherrill, Director Education, Workforce, and In...
Date March 22, 2011 Report No. GAO-11-152 Title

Davis-Bacon Act: Methodological Changes Needed to Improve Wage Survey

United States Government Accountability Office GAO March 2011 Report to the Chairman, Committee on Education and the Workforce, House of Representatives DAVIS-BACON ACT Methodological Changes Needed to Improve Wage Survey GAO-11-152 March 2011 DAVIS-BACON ACT Accountability • Integrity • Reliability Methodological Changes Needed to Improve Wage Survey Highlights of GAO-11-152, a report to the ...
Date Oct. 28, 2010 Report No. GAO-11-60 Title

Military Housing: Installations Need to Share Information on Their Section 801 On-Base Housing Contracts

United States Government Accountability Office GAO October 2010 Report to Congressional Committees MILITARY HOUSING Installations Need to Share Information on Their Section 801 On-Base Housing Contracts GAO-11-60 October 2010 MILITARY HOUSING Accountability • Integrity • Reliability Installations Need to Share Information on Their Section 801 On-Base Housing Contracts Highlights of GAO-11-60, ...
Date July 26, 2010 Report No. GAO-10-686 Title

Defense Acquisitions: Guidance Needed on Navy's Use of Investment Incentives at Private Shipyards

United States Government Accountability Office GAO July 2010 Report to the Chairman, Subcommittee on Defense, Committee on Appropriations, House of Representatives DEFENSE ACQUISITIONS Guidance Needed on Navy’s Use of Investment Incentives at Private Shipyards GAO-10-686 July 2010 DEFENSE ACQUISITIONS Highlights Highlights of GAO-10-686, a report to the Chairman, Subcommittee on Defense, Committ...
Date Dec. 14, 2009 Report No. GAO-10-189 Title

VA Construction: VA Is Working to Improve Initial Project Cost Estimates, but Should Analyze Cost and Schedule Risks

United States Government Accountability Office GAO December 2009 Report to the Ranking Member, Committee on Veterans’ Affairs, House of Representatives VA CONSTRUCTION VA Is Working to Improve Initial Project Cost Estimates, but Should Analyze Cost and Schedule Risks GAO-10-189 December 2009 VA CONSTRUCTION Highlights Highlights of GAO-10-189, a report to the Ranking Member, Committee on Veteran...
Date Sept. 17, 2009 Report No. GAO-09-1013T Title

Secure Border Initiative: Technology Deployment Delays Persist and the Impact of Border Fencing Has Not Been Assessed

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EDT Thursday, September 17, 2009 Testimony Before the Subcommittee on Border, Maritime and Global Counterterrorism, Committee on Homeland Security, House of Representatives SECURE BORDER INITIATIVE Technology Deployment Delays Persist and the Impact of Border Fencing Has Not Been Assessed Statement of...
Date Sept. 9, 2009 Report No. GAO-09-896 Title

Secure Border Initiative: Technology Deployment Delays Persist and the Impact of Border Fencing Has Not Been Assessed

United States Government Accountability Office GAO September 2009 Report to Congressional Requesters SECURE BORDER INITIATIVE Technology Deployment Delays Persist and the Impact of Border Fencing Has Not Been Assessed GAO-09-896 September 2009 SECURE BORDER INITIATIVE Highlights Highlights of GAO-09-896, a report to congressional requesters Accountability Integrity Reliability Technology Deploymen...
Date July 30, 2009 Report No. GAO-09-870R Title

United Nations: Renovation Still Scheduled for Completion in 2013, but Risk to Its Schedule and Cost Remain

United States Government Accountability Office GAO July 2009 Correspondence to the Ranking Member, Committee on Foreign Relations, U.S. Senate UNITED NATIONS Renovation Still Scheduled for Completion in 2013, but Risks to Its Schedule and Cost Remain GAO-09-870R a July 30, 2009 UNITED NATIONS Highlights Highlights of GAO-09-870R, a report to Ranking Member, Richard G. Lugar Accountability Integrit...
Date July 23, 2009 Report No. GAO-09-925T Title

Capitol Visitor Center: Construction Expected to Be Completed within Current Budget Estimate

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EDT Thursday, July 23, 2009 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, House of Representatives CAPITOL VISITOR CENTER Construction Expected to Be Completed within Current Budget Estimate Statement of Terrell G. Dorn, Director, Physical Infrastructure Iss...
Date May 13, 2009 Report No. GAO-09-322 Title

Best Practices: High Levels of Knowledge at Key Points Differentiate Commercial Shipbuilding from Navy Shipbuilding

United States Government Accountability Office GAO May 2009 Report to Congressional Committees BEST PRACTICES High Levels of Knowledge at Key Points Differentiate Commercial Shipbuilding from Navy Shipbuilding GAO-09-322 May 2009 BEST PRACTICES Highlights Highlights of GAO-09-322, a report to congressional committees Accountability Integrity Reliability High Levels of Knowledge at Key Points Diffe...
Date March 4, 2009 Report No. GAO-09-406T Title

Department of Energy: Contract and Project Management Concerns at the National Nuclear Security Administration and Office Of Environmental Management

United States Government Accountability Office GAO For Release on Delivery Expected at 2:00 p.m. EST Wednesday, March 4, 2009 Testimony Before the Subcommittee on Energy and Water Development, Committee on Appropriations, House of Representatives DEPARTMENT OF ENERGY Contract and Project Management Concerns at the National Nuclear Security Administration and Office of Environmental Management Stat...
Date Jan. 29, 2009 Report No. GAO-09-244R Title

Homeland Security: Secure Border Initiative Fence Construction Costs

United States Government Accountability Office Washington, DC 20548 January 29, 2009 Congressional Committees Subject: Secure Border Initiative Fence Construction Costs Much of the United States’ 6,000 miles of international borders with Canada and Mexico remains vulnerable to illegal entry of aliens, criminals, and cargo. The Department of Homeland Security (DHS) apprehends hundreds of thousand...
Date Jan. 16, 2009 Report No. GAO-09-48 Title

Embassy Construction: Additional Actions Are Needed to Address Contractor Participation

United States Government Accountability Office GAO January 2009 Report to Congressional Committees EMBASSY CONSTRUCTION Additional Actions Are Needed to Address Contractor Participation GAO-09-48 January 2009 EMBASSY CONSTRUCTION Highlights Highlights of GAO-09-48, a report to congressional committees Accountability Integrity Reliability Additional Actions Are Needed to Address Contractor Particip...
Date Jan. 16, 2009 Report No. GAO-09-47SP Title

New Embassy Construction: Structured Interviews with Construction Firms (GAO-09-47SP, January 2009), an E-supplement to GAO-09-48

Date Sept. 24, 2008 Report No. GAO-08-1172T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of September 24, 2008

United States Government Accountability Office GAO For Release on Delivery Expected at 11 a.m. EDT September 24, 2008 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, House of Representatives CAPITOL VISITOR CENTER Update on Status of Project's Schedule and Cost as of September 24, 2008 Statement of Terrell G. Dorn, Director, Physical Infrastructure Issues ...
Date Sept. 12, 2008 Report No. GAO-08-889 Title

Federal Courthouse Construction: Estimated Costs to House the L.A. District Court Have Tripled and There Is No Consensus on How to Proceed

United States Government Accountability Office GAO September 2008 Report to Congressional Requesters FEDERAL COURTHOUSE CONSTRUCTION Estimated Costs to House the L.A. District Court Have Tripled and There Is No Consensus on How to Proceed GAO-08-889 September 2008 FEDERAL COURTHOUSE CONSTRUCTION Highlights Highlights of GAO-08-889, a report to congressional requesters Accountability Integrity Reli...
Date July 8, 2008 Report No. GAO-08-900T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of June 27, 2008

United States Government Accountability Office GAO For Release on Delivery Expected at 7:00 p.m. EDT Tuesday, July 8, 2008 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, House of Representatives CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost as of June 27, 2008 Statement of Terrell G. Dorn, Director, Physical Infrastructure Issue...
Date June 25, 2008 Report No. GAO-08-923T Title

Military Construction: Kaiserslautern Military Community Center Project Continues to Experience Problems

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EDT Wednesday, June 25, 2008 Testimony Before the Committee on Oversight and Government Reform, House of Representatives MILITARY CONSTRUCTION Kaiserslautern Military Community Center Project Continues to Experience Problems Statement of Gregory D. Kutz, Managing Director Forensic Audits and Special I...
Date May 29, 2008 Report No. GAO-08-634 Title

Prison Construction: Clear Communication on the Accuracy of Cost Estimates and Project Changes is Needed

United States Government Accountability Office GAO May 2008 Report to the Subcommittee on Commerce, Justice, Science, and Related Agencies, Committee on Appropriations, U.S. Senate PRISON CONSTRUCTION Clear Communication on the Accuracy of Cost Estimates and Project Changes Is Needed GAO-08-634 May 2008 PRISON CONSTRUCTION Highlights Highlights of GAO-08-634, a report to the Subcommittee on Commer...
Date May 22, 2008 Report No. GAO-08-811T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of May 22, 2008

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EDT Thursday, May 22, 2008 Testimony before the Subcommittee on the Legislative Branch, Committee on Appropriations, House of Representatives CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost as of May 22, 2008 Statement of Terrell G. Dorn, Director, Physical Infrastructure Issu...
Date April 15, 2008 Report No. GAO-08-677T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of April 15, 2008

United States Government Accountability Office GAO For Release on Delivery Expected at 1:30 p.m. EDT Tuesday, April 15, 2008 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, House of Representatives CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost as of April 15, 2008 Statement of Terrell G. Dorn, Director, Physical Infrastructure Is...
Date April 1, 2008 Report No. GAO-08-602R Title

Defense Infrastructure: DOD Funding for Infrastructure and Road Improvements Surrounding Growth Installations

United States Government Accountability Office Washington, DC 20548 April 1, 2008 Congressional Committees Subject: Defense Infrastructure: DOD Funding for Infrastructure and Road Improvements Surrounding Growth Installations The Department of Defense (DOD) is simultaneously implementing a number of force realignments that contribute to personnel growth at military installations throughout the Uni...
Date March 12, 2008 Report No. GAO-08-545T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of March 12, 2008

United States Government Accountability Office GAO For Release on Delivery Expected at 1:30 p.m. EST Wednesday, March 12, 2008 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, House of Representatives CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost as of March 12, 2008 Statement of Terrell G. Dorn, Director, Physical Infrastructure ...
Date Feb. 7, 2008 Report No. GAO-08-475T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of February 7, 2008

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EST Thursday, February 7, 2008 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, House of Representatives CAPITOL VISITOR CENTER Update on Status of Project's Schedule and Cost as of February 7, 2008 Statement of Terrell G. Dorn, Director, Physical Infrastructur...
Date Nov. 14, 2007 Report No. GAO-08-227T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of October 31, 2007

United States Government Accountability Office GAO For Release on Delivery Expected at 9:00 a.m. EST Wednesday, November 14, 2007 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, House of Representatives CAPITOL VISITOR CENTER Update on Status of Project's Schedule and Cost as of October 31, 2007 Statement of Terrell G. Dorn, Director, Physical Infrastructu...
Date July 31, 2007 Report No. GAO-07-1149T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of July 31, 2007

United States Government Accountability Office GAO For Release on Delivery Expected at 9:00 a.m. EDT Tuesday, July 31, 2007 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, House of Representatives CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost as of July 31, 2007 Statement of Terrell G. Dorn, Director, Physical Infrastructure Issu...
Date June 28, 2007 Report No. GAO-07-1039T Title

Military Construction: Observations on Mismanagement of the Kaiserslautern Military Community Center

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EDT Thursday, June 28, 2007 Testimony Before the Committee on Oversight and Government Reform, House of Representatives MILITARY CONSTRUCTION Observations on Mismanagement of the Kaiserslautern Military Community Center Statement of Gregory D. Kutz, Managing Director Forensic Audits and Special Invest...
Date June 27, 2007 Report No. GAO-07-897T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of June 27, 2007

United States Government Accountability Office GAO For Release on Delivery Expected at 9:00 a.m. EDT Wednesday, June 27, 2007 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, House of Representatives CAPITOL VISITOR CENTER Update on Status of Project's Schedule and Cost as of June 27, 2007 Statement of Terrell G. Dorn, Director, Physical Infrastructure Issu...
Date April 24, 2007 Report No. GAO-07-755T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of April 17, 2007

United States Government Accountability Office GAO For Release on Delivery Expected at 1:30 p.m. EDT Tuesday, April 24, 2007 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, House of Representatives CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost as of April 17, 2007 Statement of Terrell G. Dorn, Director, Physical Infrastructure Is...
Date March 13, 2007 Report No. GAO-07-601T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of March 13, 2007

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EDT Tuesday, March 13, 2007 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, House of Representatives CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost as of March 13, 2007 Statement of Terrell G. Dorn, Director Physical Infrastructure Is...
Date Feb. 28, 2007 Report No. GAO-07-357 Title

Foreign Assistance: USAID Signature Tsunami Reconstruction Efforts in Indonesia and Sri Lanka Exceed Initial Cost and Schedule Estimates, and Face Further Risks

United States Government Accountability Office GAO February 2007 Report to Congressional Committees FOREIGN ASSISTANCE USAID Signature Tsunami Reconstruction Efforts in Indonesia and Sri Lanka Exceed Initial Cost and Schedule Estimates, and Face Further Risks GAO-07-357 February 2007 FOREIGN ASSISTANCE Highlights Highlights of GAO-07-357, a report to congressional committees Accountability Integri...
Date Feb. 16, 2007 Report No. GAO-07-507T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of February 16, 2007

United States Government Accountability Office GAO For Release on Delivery Expected at 2:30 p.m. EST Friday, February 16, 2007 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, House of Representatives CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost as of February 16, 2007 Statement of Terrell G. Dorn, Director Physical Infrastructur...
Date Feb. 15, 2007 Report No. GAO-07-426T Title

Rebuilding Iraq: Reconstruction Progress Hindered by Contracting, Security, and Capacity Challenges

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EST Thursday, February 15, 2007 Testimony before the Committee on Oversight and Government Reform, House of Representatives REBUILDING IRAQ Reconstruction Progress Hindered by Contracting, Security, and Capacity Challenges Statement of David M. Walker Comptroller General of the United States GAO-07-42...
Date Dec. 15, 2006 Report No. GAO-07-30R Title

International Affairs: Rebuilding Iraq--Status of DOD's Reconstruction Program

United States Government Accountability Office Washington, DC 20548 December 15, 2006 Congressional Committees Subject: Rebuilding Iraq—Status of DOD’s Reconstruction Program Of the $18.4 billion that Congress appropriated for Iraq relief and reconstruction in fiscal year 2004, the Department of Defense (DOD) received the largest share— $13.5 billion.1 As of September 30, 2006, DOD had oblig...
Date Nov. 15, 2006 Report No. GAO-07-129T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost As of November 15, 2006

United States Government Accountability Office GAO For Release on Delivery Expected at 2:30 p.m. EST Wednesday, November 15, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost As of November 15, 2006 Statement of Bernard L. Ungar, Director Bradley M. James, Assistant Dir...
Date Oct. 6, 2006 Report No. GAO-07-40 Title

Rebuilding Iraq: Status of Competition for Iraq Reconstruction Contracts

United States Government Accountability Office GAO October 2006 Report to Congressional Committees REBUILDING IRAQ Status of Competition for Iraq Reconstruction Contracts GAO-07-40 October 2006 REBUILDING IRAQ Highlights Highlights of GAO-07-40, a report to Congressional Committees Accountability Integrity Reliability Status of Competition for Iraq Reconstruction Contracts Why GAO Did This Study S...
Date Sept. 21, 2006 Report No. GAO-06-1058T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of September 21, 2006

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EDT Thursday, September 21, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost As of September 21, 2006 Statement of Terrell Dorn, Director Bernard L. Ungar, Director Physic...
Date Aug. 2, 2006 Report No. GAO-06-828T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost As of August 2, 2006

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EDT Wednesday, August 2, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost As of August 2, 2006 Statement of Terrell Dorn, Director Bernard L. Ungar, Director Physical Infr...
Date June 28, 2006 Report No. GAO-06-827T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost As of June 28, 2006

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EDT Wednesday, June 28, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost As of June 28, 2006 Statement of Terrell Dorn, Director Bernard L. Ungar, Director Physical Infras...
Date June 20, 2006 Report No. GAO-06-877T Title

United Nations: Weaknesses in Internal Oversight and Procurement Could Affect the Effective Implementation of the Planned Renovation

United States Government Accountability Office GAO For Release on Delivery Expected at 2:30 p.m. EDT Tuesday, June 20, 2006 Testimony Before the Subcommittee on Federal Financial Management, Government Information, and International Security UNITED NATIONS Weaknesses in Internal Oversight and Procurement Could Affect the Effective Implementation of the Planned Renovation Statement of Thomas Melito...
Date May 24, 2006 Report No. GAO-06-803T Title

Capitol Visitor Center: Update on Status of Projects's Schedule and Cost As of May 24, 2006

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EDT Wednesday, May 24, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Status of Projects’s Schedule and Cost As of May 24, 2006 Statement of Terrell Dorn, Director Bernard L. Ungar, Director Physical Infrast...
Date April 27, 2006 Report No. GAO-06-665T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of April 27, 2006

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EDT Thursday, April 27, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost as of April 27, 2006 Statement of Terrell Dorn, Director Bernard L. Ungar, Director Physical Infra...
Date March 15, 2006 Report No. GAO-06-528T Title

Capitol Visitor Center: Status of Project's Schedule and Cost as of March 15, 2006

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EST Wednesday, March 15, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Status of Project’s Schedule and Cost as of March 15, 2006 Statement of Bernard L. Ungar, Director Terrell Dorn Assistant Director Physical Infra...
Date Feb. 10, 2006 Report No. GAO-06-321R Title

Architect of the Capitol: Addressing Staffing and Training Issues Is Important for Efficient and Safe West Refrigeration Plant Operations

United States Government Accountability Office Washington, DC 20548 February 10, 2006 The Honorable Wayne Allard Chairman Subcommittee on the Legislative Branch Committee on Appropriations United States Senate The Honorable Jerry Lewis Chairman Committee on Appropriations House of Representatives Subject: Architect of the Capitol: Addressing Staffing and Training Issues Is Important for Efficient ...
Date Nov. 16, 2005 Report No. GAO-06-251T Title

Capitol Visitor Center: Update on Schedule and Cost

United States Government Accountability Office GAO For Release on Delivery Expected at 11:00 a.m. EST Wednesday, November 16, 2005 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Schedule and Cost Statement of Bernard L. Ungar, Director Terrell Dorn, Assistant Director Physical Infrastructure Issues GAO-06-251T ...
Date Oct. 18, 2005 Report No. GAO-06-180T Title

Capitol Visitor Center: Status of Schedule, Fire Protection, Cost, and Related Issues

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EDT Tuesday, October 18, 2005 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Status of Schedule, Fire Protection, Cost, and Related Issues Statement of Bernard L. Ungar, Director Terrell Dorn, Assistant Director Physical Inf...
Date Sept. 15, 2005 Report No. GAO-05-1037T Title

Capitol Visitor Center: Schedule Delays Continue; Reassessment Underway

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EDT Thursday, September 15, 2005 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Schedule Delays Continue; Reassessment Underway Statement of Bernard L. Ungar, Director Terrell Dorn, Assistant Director Physical Infrastructure...