Date Jan. 3, 1980 |
Report No. PSAD-80-15 |
Title
-BY THE COMPTROLLER GENERAL Report To The Congress
OF THE UNITED STATES NASA Should Provide The Congress Complete Cost Information On The Space Telescope Program
NASA's space telescope will be the largest, most complex space observatory ever developed. Life-cycle costs--$530 million in development costs, including $296 million for project reserves, and $600 million in operations costs to the year ... |
Date Aug. 4, 1978 |
Report No. PSAD-78-57 |
Title
DOCUMENT RESUME
06762 - (F2207225] A Second Launch Site for the Shuttle? An Analysis cf Needs for the Nation's Space Program. PSAD-78-57; B-183134. August 4, 1978. 38 pp. * 11 appendices (37 FF-). -Report to the Congress; by Elmer B. Staats, Comptroller General. Issue Area: Science and Technology: Management and Oversight of Programs (2004); Federal Procurement of Gcurds and Services: N-tifying th... |
Date March 9, 1978 |
Report No. 105609 |
Title
DOCUMENT ReSUSE
05609 - [B0765713] The Space Transportation System. arch 9, 1978. 14 pp. Testimcny before the House Committee on Appropriations: Defense Subcommittee; the House Committee on Appropriations: HUD-Independent Agencies Subcommittee; the House Coemittee on Appropriations: ilitar7 Construction Subcommittee; by Richard W. Gutmann, Director, rocurement and Systems Acquisition Div. Contact:... |
Date Nov. 7, 1977 |
Report No. PSAD-77-65 |
Title
DOCUMrEN C 234 f E3134377 ] RESUiE Natiundi (15 pp.).
zport to General. Aeronautics end Space Administraticn Should Erovide tf . C;XIqress witn More inrormationr on :'SAD-77-65; B-183134. November 7, the Fioneer Venus Ercject. 1977. 33 Ep. + 3 appendices the Congress; by Robert F. eltler, Acting Comptroller Earnageient
and oversignt Issue Area: Sci nce and TacnrLology: and Systems Programs
contact... |
Date Sept. 16, 1977 |
Report No. PSAD-77-126 |
Title
DOCUMENT RESOME 03376 - rA2653842] The SASAT-A Project: Where it Stands Today. PSAD-77-126; B-183134. September 16, 1977. 25 pp. + appendices (18 pp.). Report to the Congress; by Elmer B. Staats, Comptroller General. Issue Area: Science and Technology: Management and Oversight of Programs 2004); Federal Procurement of Goods and Services: Notifyirg the Congress of Status of Important Procurenest Pr... |
Date June 27, 1977 |
Report No. PSAD-77-114 |
Title
DOCUMENT RESUME
02740 - [A1852872] More Emphasis Needed on Data Analysis Phase of Space Science Programs. PSAD--77-114; B-133394. June 27, 1977. 17 pp. + 4 appendices (24 pp.). Report to the Congress; by Elmer B. Staats, Comptroller General. Issue Area: Science and Technology: Management and oversight of Programs (2004); Federal Procurement of Goods and Services (1900). Contact: Procurement and Sy... |
Date May 20, 1977 |
Report No. PSAD-77-103 |
Title
DOCUMENT RESUME
02130 A1452460] Statas of the Mariner Jupiter/Saturn 1977 Project. PSAD-77-103; B-183134. ay 20, 1977. 27 pp. Report to the Congress; by Elmer B. Staats, Comptroller General. Issue Area: Science and Technology: Management and Oversight of
Programs 2001). Contact: Procurement and Systems Acquisition Div. Budget Function: General Science, Space, and Technology: Space Science, Applica... |
Date May 9, 1977 |
Report No. PSAD-77-17 |
Title
DOCUMENT RESUME
02129 - [A1332314] Space Shuttle Facility Program: More Definitive Cost Information Neeled. PSAD-77-17; B-183134. May 9, 1977. 29 pp. Report to the Congress; by Elmer B. Staats, Comtroller General. Issue Area: Facilities and Material Managemert (700); Federal Procurement of Goods and Services: Notifying the Congress of Status of Important Procurement Program-i (1905);Science and Te... |
Date May 4, 1977 |
Report No. PSAD-77-98 |
Title
£CCUMENT BESUMP
02118 - [A1252250G Status and Issues Pertaining to the Proposed Deveiopment of the Space Telescope Project. PSAD-77-98. May 4, 1977. 45 pp. Peport to the Congress; by Flmer B. Staats, Comptroller General. Issue Area: Science and Technology: Management and Oversight of Programs (2004); Federal Procurement of Gocds and Services: Notifying the Ccrgress of Statts of Important Procurem... |
Date April 27, 1976 |
Report No. PSAD-76-130 |
Title
B-165118 RELEASED
APR 27 1976
LM098274 111111111 lllll11111111111111 Ill
The Honorable Frank E, Moss Chai'rman, Committee on Aeronautical and Space Sciences United States Senate 5&/83fi~ \ Your Februaw 2, 1376, letter asked w to examine of a location for its proposed lunar curatorial facility. your office wanted to knov: 7. 2. 3. 4. NASA's basis for Center, Houston, Alternative considered Opinions... |
Date April 21, 1976 |
Report No. PSAD-76-73 |
Title
L 3 cv, BY THE COMPTROLL OF THE UNITED STATE§,.s ,,_: !\ 3-u,,=1,6 i
LIBRARYSYSTEM lllllllllrllllllllllllllllllllllllllll~
LM099357 status Relatin
Space tisn
Aeronautics Administration and National Space NASA’s revised development plan is introducing risks that could result in increased costs, schedule delays, and performance degradations that were not originally envisioned. The development pla... |
Date Jan. 1, 1976 |
Report No. PSAD-76-66 |
Title
u. s. GENERAL ACCOUNTING OFFICE ” .,,, 1”; Space Telescope
National Aeronautics and Space Administration Project The Space Telescope will be the largest,most space observatory ever deveIoped. NASA expects it to signigicantly extend man’s knowledge of the universe and perhaps answer the age old question: ‘Are we alone in the universe?’
complex NASA plans to request funds in its fiscal yea... |
Date Jan. 8, 1975 |
Report No. ID-75-18 |
Title
-.... . Multiagency ID-75-18 t Y l GQMFTF?OLLEF! GENERAL
WA!SHIINGTON. OF
D.C. THE UNITED STATES 2iB48 B-179800 To the President of the Senate and the Speaker of the House of Representatives This is ‘our report concerning the progress being made It dison United States-Soviet Union cooperative programs. cusses agreements for cooperative efforts in the fields of environmental protection, space exp... |
Date May 30, 1973 |
Report No. 093832 |
Title
f + . UNSTEDST~TESGENERWLACCOUMT~NGOFFICE
WASHINGTON
FIFTH REGIONAL
FLOOR OFFiCE
L 1 803WESTI3ROADSTAEEY FALLS CHURCM,WIRC~NIA 22046 MAY3 8 1373 l . c , - Realistic eosC es%%mat%ng 55 indispensable es bath th12 Congress
and and agomzy xrxmagemen~c for seleceln,~ and evahating for 608t: cmtrol during the progoct’c3 a@$uis%tion a neu project proeerss. VRlfd lestlmates prov%de a seliabls basis for ... |
Date June 15, 1972 |
Report No. B-176104 |
Title
COMPTROLLER GENERAL
WASHINGTON, OF D.C. THE UN
20548 ~176104 Dear Mr. Miller: As the result of a series of meetings between our staffs, the General Accounting Office undertook a study to identify those National I Aeronautics and SpaceAdministration (NASA)programs susceptible to 26' d cost-benefit analysis. Your staff ex$%%Ped primary interest in one of?Z6%&&‘types of cost-benefit analysis - that... |
Date June 2, 1972 |
Report No. B-173677 |
Title
REPORT TO THE CONGRESS I
IllllllllIll11 Ill11 lllll Ill11 Ill1 Ill Ill11 Ill1 Ill11
LM096542 Cost-Benefit Analysis Used In Support Of The Space Shuttle Program
National Aeronautics and Space Administration B-173677 BYTHECOMPTROLLER GENERAL OFTHEUNITED STATES JUHE 2,19-C? COMPTROLLER GENERAL WASHINGTON, OF THE UNITED D.Ct. 20548 STATTS B- 173677 0 To the Speaker President of the Senate and the of t... |
Date July 2, 1971 |
Report No. B-171977 |
Title
fRIE. WK1dC Accir-24 I 5 " _-B- - = to be A c
t {r in et
arc fle
o: i ZeneaS i > >M-~ ' aeskept
BTA"EI a 4- CoMPTROLLEr ERAL OF TH WAUilMTro UNI1KT D.C~. 20M B-171977 Dear Senator Humphrey: JUL 2 197 In your letter received by us on February 17, 1971, you reeuesteA our comments on a letter from Mr. David R. Hammer in which he expressed concern about the increase in cost to the National Aeronautics... |
Date June 17, 1971 |
Report No. B-172192 |
Title
National Aeromautics and Space Administration COMPTROLLER GENERAL OF THE UNITED STATES JUNE 1 7 , 1 9 7 1 C o n t e n t s Page
DIGEST CHAPTER 1 1
2 INTRODUCTION COST-ESTIMATING SYSTEM COST-ESTIMATING PROCFDLIRES AND PRACTICES AT THE MARSHAU SPACE FLIGHT CENTER COST-ESTIMATING PROCEDURES AND PRACTICES AT THE MANNED SPACECRAFT CENTER 6 12
18 3 4
5 26 HEADQUARTERS REVIEW OF COST ESTIMATES
ESTIMATED C... |
Date May 28, 1971 |
Report No. B-172171 |
Title
3 II) 0 Q CQMPTROLLER GENERAL'S REPORTON NATIONAL AERONAUTICSAND SPACE ADMINISTRATION'S ACQUISITION AND UTILIZATION OF T-38 JET AIRCRAFT Manned Spacecraft Center B-172171 i l I I I I I I I I I I I I I I I I I I I I I
I I I I DIGEST ------ WHY THEREVIEW WAS' MADE
The General Accounting Office (GAO) noted that the National Aeronautics and Space Administration's (NASA) Manned Spacecraft Center at Hou... |