Summary: To help measure the quality of the 2000 Census and to possibly adjust for any errors, the U.S. Census Bureau (Bureau) conducted the Accuracy and Coverage Evaluation (A.C.E.) program. However, after obligating around $207 million for A.C.E. and its predecessor program, Integrated Coverage Measurement (I.C.M.), from fiscal years 1996 through 2001, the Bureau did not use either program to adjust the census numbers. Concerned about the amount of money the Bureau spent on I.C.M. and A.C.E. programs and what was produced in return, the subcommittee asked us to review the objectives and results of the programs, the costs of consultants, and how best to track future coverage measurement activities.
The two programs the Bureau employed to measure the quality of the 2000 Census population data did not meet their objectives. The A.C.E. program achieved results other than those laid out in the Bureau's formal objectives that highlight important lessons learned. They include (1) developing a coverage measurement methodology that is both operationally and technically feasible, (2) determining the level of geography at which coverage measurement is intended, (3) keeping stakeholders, particularly Congress, informed of the Bureau's plans, and (4) adequately testing coverage measurement methodologies. It will be important for the Bureau to consider these as its current plans for the 2010 Census include coverage evaluation to measure the accuracy of the census but not necessarily to adjust the results. Of the roughly $207 million the Bureau obligated for I.C.M./A.C.E. programs from fiscal years 1996 through 2001, we identified about $22.3 million that was obligated for contracts involving over 170 vendors. We could not identify any obligations prior to 1996 in part because the Bureau included them with its general research and development efforts and did not assign the I.C.M./A.C.E. operations unique project codes in its financial management system. To track these costs in the future, it will be important for the Bureau to (1) have a financial management system that has specific project codes to capture coverage measurement costs, (2) establish the project codes as early in the planning process as possible, and (3) monitor the usage of the codes to ensure that they are properly charged.