VA Health Care: Delays in Awarding Major Construction Contracts

  Premium   Download PDF Now (14 pages)
Report Type Reports and Testimonies
Report Date March 11, 1988
Report No. HRD-88-74
Subject
Summary:

Pursuant to a legislative requirement, GAO reviewed the Veterans Administration's (VA) compliance with regulations requiring it to: (1) award contracts for construction projects funded through appropriation acts within a certain time limit; and (2) report to Congress on awards it did not make within the time limit.

GAO found that VA: (1) for fiscal years (FY) 1984 through 1987, reported that it had not awarded contracts for 26 construction projects within the required time limits; (2) did not include four other projects in its report, since it believed that it satisfied reporting requirements by including information about those projects in its budget or by awarding partial contracts; (3) blamed most contracting delays on changes in project scope and receipt of bids which exceeded available funds; and (4) expects to award contracts for 22 of the 29 projects by the end of FY 1988. GAO believes that: (1) VA actions show no intent to refrain from using the funds; and (2) the contract delays for 29 of the 30 projects did not constitute an impoundment of budget authority.

« Return to search Government Accountability Office reports