Date Sept. 28, 2006 Report No. GAO-06-1127T Title

NASA: Sound Management and Oversight Key to Addressing Crew Exploration Vehicle Project Risks

United States Government Accountability Office GAO For Release on Delivery Expected at 2:00 p.m. EDT Thursday, September 28, 2006 Testimony before the Committee on Science, House of Representatives NASA Sound Management and Oversight Key to Addressing Crew Exploration Vehicle Project Risks Statement of Allen Li, Director, Acquisition and Sourcing Management GAO-06-1127T September 28, 2006 NASA Hig...
Date Sept. 21, 2006 Report No. GAO-06-1058T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of September 21, 2006

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EDT Thursday, September 21, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost As of September 21, 2006 Statement of Terrell Dorn, Director Bernard L. Ungar, Director Physic...
Date Sept. 15, 2006 Report No. GAO-06-1077R Title

The Nation's Long-Term Fiscal Outlook: September 2006 Update

United States Government Accountability Office GAO GAO’s Long-Term Fiscal Simulations Since 1992, GAO has published long-term fiscal simulations of what might happen to federal deficits and debt levels under varying policy assumptions. GAO developed its long-term model in response to a bipartisan request from Members of Congress who were concerned about the long-term effects of fiscal policy. In...
Date Aug. 2, 2006 Report No. GAO-06-828T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost As of August 2, 2006

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EDT Wednesday, August 2, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost As of August 2, 2006 Statement of Terrell Dorn, Director Bernard L. Ungar, Director Physical Infr...
Date July 26, 2006 Report No. GAO-06-1000T Title

Tax Compliance: Opportunities Exist to Reduce the Tax Gap Using a Variety of Approaches

United States Government Accountability Office GAO For Release on Delivery Expected at 2:00 p.m. EDT Wednesday, July 26, 2006 Testimony Before the Subcommittee on Taxation and IRS Oversight, Committee on Finance, U.S. Senate TAX COMPLIANCE Opportunities Exist to Reduce the Tax Gap Using a Variety of Approaches Statement of Michael Brostek Director, Tax Issues Strategic Issues Team GAO-06-1000T Jul...
Date July 18, 2006 Report No. GAO-06-885T Title

Global War on Terrorism: Observations on Funding, Costs, and Future Commitments

United States Government Accountability Office GAO For Release on Delivery Expected at 2:00 p.m. EDT Tuesday, July 18, 2006 Testimony Before the Subcommittee on National Security, Emerging Threats, and International Relations, Committee on Government Reform, House of Representatives GLOBAL WAR ON TERRORISM Observations on Funding, Costs, and Future Commitments Statement of David M. Walker Comptrol...
Date July 17, 2006 Report No. GAO-06-817R Title

NASA: Long-Term Commitment to and Investment in Space Exploration Program Requires More Knowledge

United States Government Accountability Office Washington, DC 20548 July 17, 2006 The Honorable Sherwood Boehlert Chairman The Honorable Bart Gordon Ranking Minority Member Committee on Science House of Representatives Subject: NASA: Long-Term Commitment to and Investment in Space Exploration Program Requires More Knowledge The National Aeronautics and Space Administration (NASA) plans to spend ne...
Date June 30, 2006 Report No. GAO-06-641 Title

Embassy Construction: State Has Made Progress Constructing New Embassies, but Better Planning Is Needed for Operations and Maintenance Requirements

United States Government Accountability Office GAO June 2006 Report to the Chairman, Committee on Foreign Relations, U.S. Senate EMBASSY CONSTRUCTION State Has Made Progress Constructing New Embassies, but Better Planning Is Needed for Operations and Maintenance Requirements GAO-06-641 June 2006 EMBASSY CONSTRUCTION Highlights Highlights of GAO-06-641, a report to the Chairman, Committee on Foreig...
Date June 28, 2006 Report No. GAO-06-827T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost As of June 28, 2006

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EDT Wednesday, June 28, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost As of June 28, 2006 Statement of Terrell Dorn, Director Bernard L. Ungar, Director Physical Infras...
Date May 25, 2006 Report No. GAO-06-761T Title

Budget Process: Better Transparency, Controls, Triggers, and Default Mechanisms Would Help to Address Our Large and Growing Long-term Fiscal Challenge

United States Government Accountability Office GAO For Release on Delivery Expected at 2:30 p.m. EDT Thursday, May 25, 2006 Testimony Before the Subcommittee on Federal Financial Management, Government Information, and International Security, Committee on Homeland Security and Governmental Affairs, U.S. Senate BUDGET PROCESS Better Transparency, Controls, Triggers, and Default Mechanisms Would Hel...
Date May 24, 2006 Report No. GAO-06-803T Title

Capitol Visitor Center: Update on Status of Projects's Schedule and Cost As of May 24, 2006

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EDT Wednesday, May 24, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Status of Projects’s Schedule and Cost As of May 24, 2006 Statement of Terrell Dorn, Director Bernard L. Ungar, Director Physical Infrast...
Date May 19, 2006 Report No. GAO-06-571 Title

Commercial Aviation: Costs and Major Factors Influencing Infrastructure Changes at U.S. Airports to Accomodate the New A380 Aircraft

United States Government Accountability Office GAO May 2006 Report to the Chairman, Subcommittee on Aviation, Committee on Transportation and Infrastructure, House of Representatives COMMERCIAL AVIATION Costs and Major Factors Influencing Infrastructure Changes at U.S. Airports to Accommodate the New A380 Aircraft GAO-06-571 May 2006 COMMERCIAL AVIATION Highlights Highlights of GAO-06-571, a repor...
Date May 15, 2006 Report No. GAO-06-516 Title

Mass Transit: Issues Related to Providing Dedicated Funding for the Washington Metropolitain Area Transit Authority

United States Government Accountability Office GAO May 2006 Report to the Chairman, Committee on Government Reform, House of Representatives MASS TRANSIT Issues Related to Providing Dedicated Funding for the Washington Metropolitan Area Transit Authority GAO-06-516 May 2006 MASS TRANSIT Highlights Highlights of GAO-06-516, a report to the Chairman, Committee on Government Reform, House of Represen...
Date April 27, 2006 Report No. GAO-06-445 Title

NASA's Deep Space Network: Current Management Structure Is Not Conducive to Effectively Matching Resources with Future Requirements

United States Government Accountability Office GAO April 2006 Report to the Ranking Minority Member, Subcommittee on Space and Aeronautics, Committee on Science, House of Representatives NASA’S DEEP SPACE NETWORK Current Management Structure Is Not Conducive to Effectively Matching Resources with Future Requirements GAO-06-445 April 2006 NASA'S DEEP SPACE NETWORK Highlights Highlights of GAO-06-...
Date April 27, 2006 Report No. GAO-06-665T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Cost as of April 27, 2006

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EDT Thursday, April 27, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Cost as of April 27, 2006 Statement of Terrell Dorn, Director Bernard L. Ungar, Director Physical Infra...
Date April 26, 2006 Report No. GAO-06-418T Title

Fiscal Year 2007 Budget Request: U.S. Government Accountability Office

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EST April 26, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate FISCAL YEAR 2007 BUDGET REQUEST: U.S. GOVERNMENT ACCOUNTABILITY OFFICE Statement of David M. Walker Comptroller General of the United States GAO-06-418T Mr. Chairman and Members of ...
Date April 4, 2006 Report No. GAO-06-572T Title

Highway Trust Fund: Overview of Highway Trust Fund Estimates

United States Government Accountability Office GAO For Release on Delivery Expected at 2:00 p.m. EST Tuesday, April 4, 2006 Testimony Before the Subcommittee on Highways, Transit, and Pipelines, Committee on Transportation and Infrastructure, U.S. House of Representatives HIGHWAY TRUST FUND Overview of Highway Trust Fund Estimates Statement of Katherine Siggerud, Director Physical Infrastructure I...
Date March 28, 2006 Report No. GAO-06-562T Title

Federal Aviation Administration: An Analysis of the Financial Viability of the Airport and Airway Trust Fund

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EST Tuesday, March 28, 2006 Testimony Before the Subcommittee on Aviation, Committee on Commerce, Science and Transportation, U.S. Senate FEDERAL AVIATION ADMINISTRATION An Analysis of the Financial Viability of the Airport and Airway Trust Fund Statement of Gerald L. Dillingham, Ph.D. Director, Physi...
Date March 15, 2006 Report No. GAO-06-528T Title

Capitol Visitor Center: Status of Project's Schedule and Cost as of March 15, 2006

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EST Wednesday, March 15, 2006 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Status of Project’s Schedule and Cost as of March 15, 2006 Statement of Bernard L. Ungar, Director Terrell Dorn Assistant Director Physical Infra...
Date March 10, 2006 Report No. GAO-06-417T Title

U.S. Government Accountability Office: Fiscal Year 2007 Budget Request

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EST March 10, 2006 Testimony Before the Committee on Appropriations, House of Representatives FISCAL YEAR 2007 BUDGET REQUEST Statement of David M. Walker Comptroller General of the United States GAO-06-417T Mr. Chairman and Members of the Committee: I am pleased to appear before the Committee today i...
Date Feb. 15, 2006 Report No. GAO-06-456T Title

21st Century: Addressing Long-Term Fiscal Challenges Must Include a Re-examination of Mandatory Spending

United States Government Accountability Office GAO For Release on Delivery Expected at 2:00 p.m. EST Wednesday, February 15, 2006 Testimony Before the Budget Committee, House of Representatives 21ST CENTURY Addressing Long-Term Fiscal Challenges Must Include a Re-examination of Mandatory Spending Statement of David M. Walker Comptroller General of the United States GAO-06-456T Mr. Chairman, Repres...
Date Feb. 15, 2006 Report No. GAO-06-453T Title

Tax Gap: Making Significant Progress in Improving Tax Compliance Rests on Enhancing Current IRS Techniques and Adopting New Legislative Actions

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EST Wednesday, February 15, 2006 Testimony Before the Committee on Budget, U.S. Senate TAX GAP Making Significant Progress in Improving Tax Compliance Rests on Enhancing Current IRS Techniques and Adopting New Legislative Actions Statement of David M. Walker Comptroller General of the United States GA...
Date Dec. 5, 2005 Report No. GAO-06-195 Title

Student Consolidation Loans: Potential Effects of Making Fiscal Year 2006 Consolidation Loans Exclusively through the Direct Loan Program

United States Government Accountability Office GAO December 2005 Report to the Ranking Minority Member, Committee on Education and the Workforce, House of Representatives STUDENT CONSOLIDATION LOANS Potential Effects of Making Fiscal Year 2006 Consolidation Loans Exclusively through the Direct Loan Program GAO-06-195 December 2005 STUDENT CONSOLIDATION LOANS Highlights Highlights of GAO-06-195, a ...
Date Nov. 16, 2005 Report No. GAO-06-249T Title

Polar-Orbiting Operational Environmental Satellites: Technical Problems, Cost Increases, and Schedule Delays Trigger Need for Difficult Trade-off Decisions

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EST Wednesday, November 16, 2005 Testimony Before the Committee on Science, House of Representatives POLAR-ORBITING OPERATIONAL ENVIRONMENTAL SATELLITES Technical Problems, Cost Increases, and Schedule Delays Trigger Need for Difficult Trade-off Decisions Statement of David A. Powner, Director Informa...
Date Nov. 16, 2005 Report No. GAO-06-251T Title

Capitol Visitor Center: Update on Schedule and Cost

United States Government Accountability Office GAO For Release on Delivery Expected at 11:00 a.m. EST Wednesday, November 16, 2005 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Schedule and Cost Statement of Bernard L. Ungar, Director Terrell Dorn, Assistant Director Physical Infrastructure Issues GAO-06-251T ...
Date Oct. 20, 2005 Report No. GAO-06-61R Title

U.S. Securities and Exchange Commission: Building Project Management and Related Budget Planning

United States Government Accountability Office Washington, DC 20548 October 20, 2005 The Honorable Frank R. Wolf Chairman Subcommittee on Science, the Departments of State, Justice, and Commerce, and Related Agencies Committee on Appropriations House of Representatives Subject: U.S. Securities and Exchange Commission: Building Project Management and Related Budget Planning Dear Mr. Wolf: You asked...
Date Sept. 29, 2005 Report No. GAO-05-926 Title

Force Structure: Actions Needed to Improve Estimates and Oversight of Costs for Transforming Army to a Modular Force

United States Government Accountability Office GAO September 2005 Report to Congressional Committees FORCE STRUCTURE Actions Needed to Improve Estimates and Oversight of Costs for Transforming Army to a Modular Force GAO-05-926 a September 2005 FORCE STRUCTURE Highlights Highlights of GAO-05-926, a report to congressional committees Accountability Integrity Reliability Actions Needed to Improve Es...
Date Sept. 2, 2005 Report No. GAO-05-875 Title

Mortgage Financing: FHA's $7 Billion Reestimate Reflects Higher Claims and Changing Loan and Performance Estimates

United States Government Accountability Office GAO September 2005 Report to the Chairman, Subcommittee on Housing and Community Opportunity, Committee on Financial Services, House of Representatives MORTGAGE FINANCING FHA’s $7 Billion Reestimate Reflects Higher Claims and Changing Loan Performance Estimates GAO-05-875 a September 2005 MORTGAGE FINANCING Highlights Highlights of GAO-05-875, a rep...
Date Aug. 4, 2005 Report No. GAO-05-962R Title

Military Transformation: Actions Needed by DOD to More Clearly Identify New Triad Spending and Develop a Long-term Investment Approach

United States Government Accountability Office Washington, DC 20548 August 4, 2005 The Honorable Terry Everett Chairman The Honorable Silvestre Reyes Ranking Member Subcommittee on Strategic Forces Committee on Armed Services House of Representatives Subject: Military Transformation: Actions Needed by DOD to More Clearly Identify New Triad Spending and Develop a Long-term Investment Approach In re...
Date July 28, 2005 Report No. GAO-05-922T Title

Mass Transit: Preliminary Views on Options for Additional Fiscal Oversight of the Washington Metropolitan Area Transit Authority

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EDT Thursday, July 28, 2005 Testimony Before the Committee on Government Reform, House of Representatives MASS TRANSIT Preliminary Views on Options for Additional Fiscal Oversight of the Washington Metropolitan Area Transit Authority Statement of Katherine Siggerud, Director Physical Infrastructure Is...
Date July 28, 2005 Report No. GAO-05-816R Title

Business, Industry, and Consumers: Ultimate Effects of McCarran-Ferguson Federal Antitrust Exemption on Insurer Activity are Unclear

United States Government Accountability Office Washington, DC 20548 July 28, 2005 The Honorable Michael G. Oxley Chairman Committee on Financial Services House of Representatives Subject: Ultimate Effects of McCarran-Ferguson Federal Antitrust Exemption on Insurer Activity are Unclear This letter transmits to you our briefing slides describing the potential effects of the federal antitrust exempti...
Date July 14, 2005 Report No. GAO-05-910T Title

Capitol Visitor Center: Update on Status of Project's Schedule and Costs

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EDT Thursday, July 14, 2005 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Update on Status of Project’s Schedule and Costs Statement of Bernard L. Ungar, Director Terrell Dorn, Assistant Director Physical Infrastructure I...
Date June 30, 2005 Report No. GAO-05-540 Title

Military Transformation: Actions Needed by DOD to More Clearly Identify New Triad Spending and Develop a Long-term Investment Approach

United States Government Accountability Office GAO June 2005 Report to the Subcommittee on Strategic Forces, Committee on Armed Services, House of Representatives MILITARY TRANSFORMATION Actions Needed by DOD to More Clearly Identify New Triad Spending and Develop a Long-term Investment Approach GAO-05-540 a June 2005 MILITARY TRANSFORMATION Highlights Highlights of GAO-05-540, a report to the Sub...
Date June 23, 2005 Report No. GAO-05-724 Title

Air Traffic Operations: The Federal Aviation Administration Needs to Address Major Air Traffic Operating Cost Control Changes

United States Government Accountability Office GAO June 2005 Report to Congressional Requesters AIR TRAFFIC OPERATIONS The Federal Aviation Administration Needs to Address Major Air Traffic Operating Cost Control Challenges GAO-05-724 a June 2005 AIR TRAFFIC OPERATIONS Highlights Highlights of GAO-05-724, a report to congressional requesters Accountability Integrity Reliability The Federal Aviatio...
Date June 14, 2005 Report No. GAO-05-811T Title

Capitol Visitor Center: Effective Schedule Management and Updated Cost Information Are Needed

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EDT Tuesday, June 14, 2005 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate CAPITOL VISITOR CENTER Effective Schedule Management and Updated Cost Information Are Needed Statement of Bernard L. Ungar, Director Terrell Dorn, Assistant Director Physica...
Date June 14, 2005 Report No. GAO-05-709T Title

21st Century Challenges: Performance Budgeting Could Help Promote Necessary Reexamination

United States Government Accountability Office GAO For Release on Delivery Expected at 2:00 p.m. EDT Tuesday, June 14, 2005 Testimony Before the Subcommittee on Federal Financial Management, Government Information, and International Security, Committee on Homeland Security and Governmental Affairs, U.S. Senate 21ST CENTURY CHALLENGES Performance Budgeting Could Help Promote Necessary Reexamination...
Date June 9, 2005 Report No. GAO-05-772T Title

Private Pensions: The Pension Benefit Guaranty Corporation and Long-Term Budgetary Challenges

United States Government Accountability Office GAO For Release on Delivery Expected at 9:30 a.m. EDT Thursday, June 9, 2005 Testimony before the Committee on the Budget, House of Representatives PRIVATE PENSIONS: The Pension Benefit Guaranty Corporation and Long-Term Budgetary Challenges Statement of David M. Walker Comptroller General of the United States GAO-05-772T June 9, 2005 PRIVATE PENSIONS...
Date May 23, 2005 Report No. GAO-05-447T Title

Fiscal Year 2006 Budget Request: U.S. Government Accountability Office

United States Government Accountability Office GAO For Release on Delivery Expected at 2:00 p.m. EDT Monday, May 23, 2005 Testimony Before the Committee on Appropriations, House of Representatives FISCAL YEAR 2006 BUDGET REQUEST U.S. Government Accountability Office Statement of David M. Walker Comptroller General of the United States GAO-05-447T Mr. Chairman and Members of the Committee: I am ple...
Date May 4, 2005 Report No. GAO-05-657T Title

Airport and Airway Trust Fund: Preliminary Observations on Past, Present, and Future

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EDT Wednesday, May 4, 2005 Testimony Before the Subcommittee on Aviation, Committee on Transportation and Infrastructure, House of Representatives AIRPORT AND AIRWAY TRUST FUND Preliminary Observations on Past, Present, and Future Statement of Gerald L. Dillingham, Ph.D. Director, Physical Infrastruct...
Date April 27, 2005 Report No. GAO-05-564T Title

Long-Term Care Financing: Growing Demand and Cost of Services Are Straining Federal and State Budgets

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EDT Wednesday, April 27, 2005 Testimony Before the Subcommittee on Health, Committee on Energy and Commerce, House of Representatives LONG-TERM CARE FINANCING Growing Demand and Cost of Services Are Straining Federal and State Budgets Statement of Kathryn G. Allen Director, Health Care—Medicaid and ...
Date April 19, 2005 Report No. GAO-05-476T Title

Fiscal Year 2006 Budget Request: U.S. Government Accountability Office

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EDT Tuesday, April 19, 2005 Testimony Before the Subcommittee on the Legislative Branch, Committee on Appropriations, U.S. Senate FISCAL YEAR 2006 BUDGET REQUEST U.S. Government Accountability Office Statement of David M. Walker Comptroller General of the United States GAO-05-476T Mr. Chairman and Mem...
Date April 14, 2005 Report No. GAO-05-527T Title

Tax Compliance: Reducing the Tax Gap Can Contribute to Fiscal Sustainability but Will Require a Variety of Strategies

United States Government Accountability Office GAO For Release on Delivery Expected at 10:00 a.m. EDT Thursday, April 14, 2005 Testimony Before the Committee on Finance, U.S. Senate TAX COMPLIANCE Reducing the Tax Gap Can Contribute to Fiscal Sustainability but Will Require a Variety of Strategies Statement of David M. Walker Comptroller General of the United States GAO-05-527T A April 14, 2005 TA...
Date April 13, 2005 Report No. GAO-05-333SP Title

National Airspace System: Experts' Views on Improving the U.S. Air Traffic Control Modernization Program

United States Government Accountability Office GAO April 2005 GAO Panel NATIONAL AIRSPACE SYSTEM Experts’ Views on Improving the U.S. Air Traffic Control Modernization Program GAO-05-333SP a April 2005 NATIONAL AIRSPACE SYSTEM Highlights Highlights of GAO-05-333SP Accountability Integrity Reliability Experts’ Views on Improving the U.S. Air Traffic Control Modernization Program Why GAO Convene...
Date March 31, 2005 Report No. GAO-05-300 Title

Results-Oriented Government: Improvements to DHS's Planning Process Would Enhance Usefulness and Accountability

United States Government Accountability Office GAO March 2005 Report to the Chairman, Subcommittee on National Security, Emerging Threats and International Relations, Committee on Government Reform, House of Representatives RESULTS-ORIENTED GOVERNMENT Improvements to DHS’s Planning Process Would Enhance Usefulness and Accountability GAO-05-300 a March 2005 RESULTS-ORIENTED GOVERNMENT Highlights ...
Date March 31, 2005 Report No. GAO-05-454 Title

Unfunded Mandates: Views Vary About Reform Act's Strengths, Weaknesses, and Options for Improvement

United States Government Accountability Office GAO March 2005 Report to the Chairman, Subcommittee on Oversight of Government Management, the Federal Workforce and the District of Columbia, Committee on Homeland Security and Governmental Affairs, U.S. Senate UNFUNDED MANDATES Views Vary About Reform Act’s Strengths, Weaknesses, and Options for Improvement GAO-05-454 a March 2005 UNFUNDED MANDATE...
Date March 16, 2005 Report No. GAO-05-443T Title

Force Structure: Preliminary Observations on Army Plans to Implement and Fund Modular Forces

United States Government Accountability Office GAO For Release on Delivery Expected at time 2:30 p.m. EST Wednesday, March 16, 2005 Testimony Before the Subcommittee on Tactical Air and Land Forces, Committee on Armed Services, House of Representatives FORCE STRUCTURE Preliminary Observations on Army Plans to Implement and Fund Modular Forces Statement of Sharon Pickup Director, Defense Capabiliti...
Date March 15, 2005 Report No. GAO-05-227 Title

Housing Finance: Options to Help Prevent Suspensions of FHA and RHS Loan Guarantee Programs

United States Government Accountability Office GAO March 2005 Report to the Chairman, Subcommittee on Housing and Community Opportunity, Committee on Financial Services, House of Representatives HOUSING FINANCE Options to Help Prevent Suspensions of FHA and RHS Loan Guarantee Programs GAO-05-227 a March 2005 HOUSING FINANCE Highlights Highlights of GAO-05-227, a report to the Chairman, Subcommitte...
Date March 9, 2005 Report No. GAO-05-397T Title

Social Security Reform: Early Action Would be Prudent

United States Government Accountability Office GAO For Release on Delivery Expected at 10:30 a.m. EST Wednesday, March 9, 2005 Testimony Before the Committee on Ways and Means, House of Representatives SOCIAL SECURITY REFORM Early Action Would Be Prudent Statement of David M. Walker Comptroller General of the United States GAO-05-397T A March 9, 2005 SOCIAL SECURITY REFORM Highlights Highlights of...
Date March 3, 2005 Report No. GAO-05-390T Title

Tactical Aircraft: Status of the F/A-22 and JSF Acquisition Programs and Implications for Tactical Aircraft Modernization

United States Government Accountability Office GAO For Release on Delivery Expected at 9:00 a.m. EST Thursday, March 3, 2005 Testimony Before the Subcommittee on Tactical Air and Land Forces, Committee on Armed Services, House of Representatives TACTICAL AIRCRAFT Status of the F/A-22 and JSF Acquisition Programs and Implications for Tactical Aircraft Modernization Statement of Michael Sullivan and...
Date Feb. 28, 2005 Report No. GAO-05-242 Title

NASA's Space Vision: Business Case for Prometheus 1 Needed to Ensure Requirements Match Available Resources

United States Government Accountability Office GAO February 2005 Report to Congressional Requesters NASA’S SPACE VISION Business Case for Prometheus 1 Needed to Ensure Requirements Match Available Resources GAO-05-242 February 2005 NASA'S SPACE VISION Highlights Highlights of GAO-05-242, a report to congressional requesters Accountability Integrity Reliability Business Case for Prometheus 1 Need...