December 2011 United States Government Accountability Office Report to the Committee on Armed Services, U.S. Senate DEFENSE CONTRACT AUDITS Actions Needed to Improve DCAA's Access to and Use of Defense Company Internal Audit Reports GAO-12-88 December 2011 DEFENSE CONTRACT AUDITS
Actions Needed to Improve DCAA’s Access to and Use of Defense Company Internal Audit Reports
Highlights of GAO-12... |
Date Nov. 16, 2011 |
Report No. GAO-12-232T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 1:30 p.m. EST Wednesday, November 16, 2011 Testimony
Before the Subcommittee on Technology, Information Policy, Intergovernmental Relations and Procurement Reform, Committee on Oversight and Government Reform, House of Representatives ACQUISITION WORKFORCE DOD’s Efforts to Rebuild Capacity Have Shown Some Prog... |
Date Nov. 3, 2011 |
Report No. GAO-12-83 |
Title
United States Government Accountability Office GAO
November 2011 Report to Congressional Requesters DEFENSE CONTRACT MANAGEMENT AGENCY Amid Ongoing Efforts to Rebuild Capacity, Several Factors Present Challenges in Meeting Its Missions GAO-12-83 November 2011 DEFENSE CONTRACT MANAGEMENT AGENCY
Amid Ongoing Efforts to Rebuild Capacity, Several Factors Present Challenges in Meeting Its Missions
High... |
Date Sept. 26, 2011 |
Report No. GAO-11-923R |
Title
United States Government Accountability Office Washington, DC 20548 September 26, 2011 Congressional Committees Subject: DOD Met Statutory Reporting Requirements on Public-Private Competitions The Department of Defense (DOD) relies on a multisector workforce of military personnel, other federal employees, and private contractors to perform needed services. The contractor workforce is substantial: ... |
Date Sept. 16, 2011 |
Report No. GAO-11-774 |
Title
United States Government Accountability Office GAO
September 2011 Report to Congressional Addressees IRAQ DRAWDOWN Opportunities Exist to Improve Equipment Visibility, Contractor Demobilization, and Clarity of Post-2011 DOD Role GAO-11-774 September 2011 IRAQ DRAWDOWN
Opportunities Exist to Improve Equipment Visibility, Contractor Demobilization, and Clarity of Post-2011 DOD Role Highlights of GAO... |
Date Sept. 15, 2011 |
Report No. GAO-11-886 |
Title
United States Government Accountability Office GAO
September 2011 Report to Congressional Committees IRAQ AND AFGHANISTAN DOD, State, and USAID Cannot Fully Account for Contracts, Assistance Instruments, and Associated Personnel GAO-11-886 September 2011 IRAQ AND AFGHANISTAN
DOD, State, and USAID Cannot Fully Account for Contracts, Assistance Instruments, and Associated Personnel Highlights of GAO... |
Date Sept. 7, 2011 |
Report No. GAO-11-777 |
Title
United States Government Accountability Office GAO
September 2011 Report to Congressional Requesters TELECOMMUNICATIONS Competition, Capacity, and Costs in the Fixed Satellite Services Industry GAO-11-777 September 2011 TELECOMMUNICATIONS
Accountability • Integrity • Reliability Competition, Capacity, and Costs in the Fixed Satellite Services Industry
Highlights of GAO-11-777, a report to cong... |
Date June 30, 2011 |
Report No. GAO-11-771T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:00 a.m. EDT Thursday, June 30, 2011 Testimony Before the Subcommittee on Contracting Oversight, Committee on Homeland Security and Governmental Affairs, U.S. Senate OPERATIONAL CONTRACT SUPPORT Actions Needed to Address Contract Oversight and Vetting of Non-U.S. Vendors in Afghanistan
Statement of William M. ... |
Date June 24, 2011 |
Report No. GAO-11-404 |
Title
United States Government Accountability Office GAO
June 2011 Report to the Ranking Member, Subcommittee on National Security, Homeland Defense and Foreign Operations, Committee on Oversight and Government Reform, House of Representatives SPACE AND MISSILE DEFENSE ACQUISITIONS Periodic Assessment Needed to Correct Parts Quality Problems in Major Programs GAO-11-404 June 2011 SPACE AND MISSILE DEFEN... |
Date June 13, 2011 |
Report No. GAO-11-717R |
Title
United States Government Accountability Office Washington, DC 20548 June 13, 2011 Congressional Committees Subject: Legislative Restrictions on Contractor Use of Mandatory Arbitration Agreements Have Had No Reported Impacts on National Security Section 8102 of the Department of Defense (DOD) and Full-Year Continuing Appropriations Act for fiscal year 2011 directed us to evaluate the effect on nati... |
Date June 8, 2011 |
Report No. GAO-11-355 |
Title
United States Government Accountability Office GAO
June 2011 Report to Congressional Addressees AFGHANISTAN U.S. Efforts to Vet Non-U.S. Vendors Need Improvement GAO-11-355 June 2011 AFGHANISTAN
Accountability • Integrity • Reliability U.S. Efforts to Vet Non-U.S. Vendors Need Improvement
Highlights of GAO-11-355, a report to congressional addressees Why GAO Did This Study
The Departments of D... |
Date April 25, 2011 |
Report No. GAO-11-580 |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 9:30 a.m. EDT Monday, April 25, 2011 Statement before the Commission on Wartime Contracting in Iraq and Afghanistan CONTINGENCY CONTRACTING Observations on Actions Needed to Address Systemic Challenges
Statement of Paul L. Francis, Managing Director Acquisition and Sourcing Management GAO-11-580 April 25, 2011 C... |
Date Feb. 1, 2011 |
Report No. GAO-11-331T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 2:30 p.m. EST Tuesday, February 1, 2011 Testimony before the Subcommittee on Contracting Oversight, Committee on Homeland Security and Governmental Affairs, U.S. Senate CONTRACT AUDITS Role in Helping Ensure Effective Oversight and Reducing Improper Payments
Statement of Jeanette M. Franzel Managing Director Acc... |
Date Jan. 14, 2011 |
Report No. GAO-11-192 |
Title
United States Government Accountability Office GAO
January 2011 Report to Congressional Committees DEFENSE ACQUISITIONS Further Action Needed to Better Implement Requirements for Conducting Inventory of Service Contract Activities GAO-11-192 January 2011 DEFENSE ACQUISITIONS
Accountability • Integrity • Reliability Further Action Needed to Better Implement Requirements for Conducting Inventory... |
Date Nov. 30, 2010 |
Report No. GAO-11-122R |
Title
United States Government Accountability Office Washington, DC 20548 November 30, 2010 Mr. Shay Assad Director, Defense Procurement and Acquisition Policy Department of Defense Subject: DOD Components Are Not Sending Required Information on Contract Awards to the Office of Public Affairs During the course of a recent engagement reviewing noncompetitive contracting, we found that departments and age... |
Date Oct. 28, 2010 |
Report No. GAO-11-61R |
Title
United States Government Accountability Office Washington, DC 20548 October 28, 2010 The Honorable Carl Levin Chairman The Honorable John McCain Ranking Member Committee on Armed Services United States Senate The Honorable Ike Skelton Chairman The Honorable Howard P. McKeon Ranking Member Committee on Armed Services House of Representatives Subject: DEFENSE ACQUISITIONS: Additional Guidance Needed... |
Date Oct. 1, 2010 |
Report No. GAO-11-1 |
Title
United States Government Accountability Office GAO
October 2010 Report to Congressional Committees IRAQ AND AFGHANISTAN DOD, State, and USAID Face Continued Challenges in Tracking Contracts, Assistance Instruments, and Associated Personnel GAO-11-1 October 2010 IRAQ AND AFGHANISTAN
Accountability • Integrity • Reliability DOD, State, and USAID Face Continued Challenges in Tracking Contracts, A... |
Date Sept. 15, 2010 |
Report No. GAO-10-1020R |
Title
United States Government Accountability Office Washington, DC 20548 September 15, 2010 The Honorable Carl Levin Chairman Committee on Armed Services United States Senate Subject: Joint Strike Fighter: Assessment of DOD’s Funding Projection for the F136 Alternate Engine Dear Senator Levin: The Joint Strike Fighter (JSF) program began in 1996 with an acquisition strategy that called for a competit... |
Date July 26, 2010 |
Report No. GAO-10-686 |
Title
United States Government Accountability Office GAO
July 2010 Report to the Chairman, Subcommittee on Defense, Committee on Appropriations, House of Representatives DEFENSE ACQUISITIONS Guidance Needed on Navy’s Use of Investment Incentives at Private Shipyards GAO-10-686 July 2010 DEFENSE ACQUISITIONS Highlights
Highlights of GAO-10-686, a report to the Chairman, Subcommittee on Defense, Committ... |
Date June 29, 2010 |
Report No. GAO-10-829T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:00 a.m. EDT Tuesday, June 29, 2010 Testimony Before the Subcommittee on National Security and Foreign Affairs, Committee on Oversight and Government Reform, House of Representatives WARFIGHTER SUPPORT Cultural Change Needed to Improve How DOD Plans for and Manages Operational Contract Support
Statement of Wil... |
Date June 25, 2010 |
Report No. GAO-10-842T |
Title
United States Government Accountability Office GAO
June 25, 2010 Testimony Before the Subcommittee on Defense, Committee on Appropriations, House of Representatives WARFIGHTER SUPPORT Preliminary Observations on DOD's Progress and Challenges in Distributing Supplies and Equipment to Afghanistan
Statement of William M. Solis, Director Defense Capabilities and Management A classified version of this... |
Date April 12, 2010 |
Report No. GAO-10-357 |
Title
United States Government Accountability Office GAO
April 2010 Report to Congressional Committees CONTINGENCY CONTRACTING Improvements Needed in Management of Contractors Supporting Contract and Grant Administration in Iraq and Afghanistan GAO-10-357 April 2010 CONTINGENCY CONTRACTING Highlights
Highlights of GAO-10-357, a report to congressional committees Accountability Integrity Reliability Impr... |
Date March 30, 2010 |
Report No. GAO-10-472 |
Title
United States Government Accountability Office GAO
March 2010 Report to Congressional Committees WARFIGHTER SUPPORT DOD Needs to Improve Its Planning for Using Contractors to Support Future Military Operations GAO-10-472 March 2010 WARFIGHTER SUPPORT Highlights
Highlights of GAO-10-472, a report to congressional committees Accountability Integrity Reliability DOD Needs to Improve Its Planning for ... |
Date March 29, 2010 |
Report No. GAO-10-389 |
Title
United States Government Accountability Office GAO
March 2010 Report to Congressional Requesters DEFENSE SUPPLIER BASE DOD Should Leverage Ongoing Initiatives in Developing Its Program to Mitigate Risk of Counterfeit Parts GAO-10-389 March 2010 DEFENSE SUPPLIER BASE Highlights
Highlights of GAO-10-389, a report to congressional requesters Accountability Integrity Reliability DOD Should Leverage On... |
Date March 23, 2010 |
Report No. GAO-10-509T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 2:00 p.m. EDT Tuesday, March 23, 2010 Testimony Before the Subcommittee on Oversight and Investigations, Committee on Armed Services, House of Representatives IRAQ AND AFGHANISTAN Agencies Face Challenges in Tracking Contracts, Grants, Cooperative Agreements, and Associated Personnel
Statement of John P. Hutton,... |
Date March 17, 2010 |
Report No. GAO-10-551T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 1:30 p.m. EDT Wednesday, March 17, 2010 Testimony Before the Subcommittee on Defense, Committee on Appropriations, House of Representatives WARFIGHTER SUPPORT Continued Actions Needed by DOD to Improve and Institutionalize Contractor Support in Contingency Operations
Statement of William M. Solis, Director Defen... |
Date March 11, 2010 |
Report No. GAO-10-520T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:00 a.m. EST Thursday, March 11, 2010 Testimony Before the Committee on Armed Services, U.S. Senate JOINT STRIKE FIGHTER Significant Challenges Remain as DOD Restructures Program
Statement of Michael Sullivan, Director Acquisition and Sourcing Management GAO-10-520T Mr. Chairman and Members of the Committee: T... |
Date March 4, 2010 |
Report No. GAO-10-266R |
Title
United States Government Accountability Office Washington, DC 20548 March 4, 2010 Congressional Committees Warfighter Support: A Cost Comparison of Using State Department Employees versus Contractors for Security Services in Iraq The U.S. government’s reliance on contractors, including the State Department’s and Department of Defense’s (DOD) use of private security contractors in Iraq, has b... |
Date Jan. 29, 2010 |
Report No. GAO-10-350R |
Title
United States Government Accountability Office Washington, DC 20548 January 29, 2010 Congressional Committees Subject: Defense Acquisitions: Observations on the Department of Defense Service Contract Inventories for Fiscal Year 2008
The Department of Defense (DOD) is the federal government’s largest purchaser of contractor-provided services and relies on contractors to support its varied mission... |
Date Jan. 27, 2010 |
Report No. GAO-10-317R |
Title
United States Government Accountability Office Washington, DC 20548 January 27, 2010 The Honorable Sherrod Brown Chairman Subcommittee on Economic Policy Committee on Banking, Housing, and Urban Affairs United States Senate The Honorable Evan Bayh Chairman Subcommittee on Security and International Trade and Finance Committee on Banking, Housing, and Urban Affairs United States Senate Subject: DOD... |
Date Jan. 20, 2010 |
Report No. GAO-10-374T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 1:30 p.m. EST Wednesday, January 20, 2010 Testimony Before the Subcommittee on Defense, Committee on Appropriations, House of Representatives DEFENSE ACQUISITIONS Managing Risk to Achieve Better Outcomes
Statement of Paul Francis, Managing Director Acquisition and Sourcing Management Michael Golden, Managing Ass... |
Date Nov. 2, 2009 |
Report No. GAO-10-179 |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 9:30 a.m. EST November 2, 2009 Statement Before the Commission on Wartime Contracting in Iraq and Afghanistan OPERATION IRAQI FREEDOM Preliminary Observations on DOD Planning for the Drawdown of U.S. Forces from Iraq
Statement of William M. Solis, Director Defense Capabilities and Management GAO-10-179 November ... |
Date Oct. 15, 2009 |
Report No. GAO-10-163T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 8:00 a.m. EDT Thursday, October 15, 2009 Testimony Before the Panel on Defense Acquisition Reform, Committee on Armed Services, House of Representatives DEFENSE MANAGEMENT Widespread DCAA Audit Problems Leave Billions of Taxpayer Dollars Vulnerable to Fraud, Waste, Abuse, and Mismanagement
Statement of Gregory D... |
Date Sept. 24, 2009 |
Report No. GAO-09-1040T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 9:30 a.m. EDT Thursday, September 24, 2009 Testimony Before the Defense Acquisition Reform Panel, Committee on Armed Services, House of Representatives DEFENSE ACQUISITIONS Sound Practices Critical to Ensuring Value for the Defense Logistics Agency’s Acquisitions
Statement of William M. Solis, Director Defense... |
Date Sept. 22, 2009 |
Report No. GAO-09-591 |
Title
United States Government Accountability Office GAO
September 2009 Report to Congressional Committees DEFENSE CONTRACTING INTEGRITY Opportunities Exist to Improve DOD’s Oversight of Contractor Ethics Programs GAO-09-591 September 2009 DEFENSE CONTRACTING INTEGRITY Highlights
Highlights of GAO-09-591, a report to congressional committees Accountability Integrity Reliability Opportunities Exist to ... |
Date Sept. 22, 2009 |
Report No. GAO-09-646SP |
Title
|
Date July 31, 2009 |
Report No. GAO-09-351 |
Title
United States Government Accountability Office GAO
July 2009 Report to Congressional Committees CONTINGENCY CONTRACT MANAGEMENT DOD Needs to Develop and Finalize Background Screening and Other Standards for Private Security Contractors GAO-09-351 July 2009 CONTINGENCY CONTRACT MANAGEMENT Highlights
Highlights of GAO-09-351, a report to congressional committees Accountability Integrity Reliability ... |
Date May 20, 2009 |
Report No. GAO-09-705T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 2:00 p.m. EDT Wednesday, May 20, 2009 Testimony Before the Subcommittee on Strategic Forces, Committee on Armed Services, U.S. Senate SPACE ACQUISITIONS DOD Faces Substantial Challenges in Developing New Space Systems
Statement of Cristina T. Chaplain, Director Acquisition and Sourcing Management GAO-09-705T May... |
Date May 20, 2009 |
Report No. GAO-09-711T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 2::30 p.m. EDT Wednesday, May 20, 2009 Testimony Before the Subcommittee on Air and Land Forces, Committee on Armed Services, House of Representatives JOINT STRIKE FIGHTER Strong Risk Management Essential as Program Enters Most Challenging Phase
Statement of Michael Sullivan, Director Acquisition and Sourcing Ma... |
Date May 18, 2009 |
Report No. GAO-09-615 |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:00 a.m. EDT Tuesday, May 19, 2009 Testimony Before the Subcommittee on Insular Affairs, Oceans and Wildlife, Committee on Natural Resources, House of Representatives COMMONWEALTH OF THE NORTHERN MARIANA ISLANDS Coordinated Federal Decisions and Additional Data Are Needed to Manage Potential Economic Impact of... |
Date April 30, 2009 |
Report No. GAO-09-648T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 1:00 p.m. EDT Thursday, April 30, 2009 Testimony Before the Subcommittee on Strategic Forces, Committee on Armed Services, House of Representatives SPACE ACQUISITIONS Government and Industry Partners Face Substantial Challenges in Developing New DOD Space Systems
Statement of Cristina Chaplain, Director Acquisit... |
Date April 28, 2009 |
Report No. GAO-09-616T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:00 a.m. EDT Tuesday, April 28, 2009 Testimony Before the Oversight and Investigations Subcommittee, Committee on Armed Services, House of Representatives ACQUISITION WORKFORCE DOD Can Improve Its Management and Oversight by Tracking Data on Contractor Personnel and Taking Additional Actions
Statement of John ... |
Date April 23, 2009 |
Report No. GAO-09-643T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 8:00 a.m. EDT Thursday, April 23, 2009 Testimony Before the Defense Acquisition Reform Panel, Committee on Armed Services, U.S. House of Representatives DEFENSE ACQUISITIONS Actions Needed to Ensure Value for Service Contracts
Statement of John Hutton, Director, Acquisition and Sourcing Management and William So... |
Date April 23, 2009 |
Report No. GAO-09-374 |
Title
United States Government Accountability Office GAO
April 2009 Report to Congressional Requesters FEDERAL CONTRACTORS Better Performance Information Needed to Support Agency Contract Award Decisions GAO-09-374 April 2009 FEDERAL CONTRACTORS Highlights
Highlights of GAO-09-374, a report to congressional requesters Accountability Integrity Reliability Better Performance Information Needed to Support ... |
Date April 1, 2009 |
Report No. GAO-09-538T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 1:00 p.m. EDT Wednesday, April 1, 2009 Testimony Before the Subcommittee on Oversight and Investigations, Committee on Armed Services, House of Representatives CONTINGENCY CONTRACTING DOD, State, and USAID Are Taking Actions to Track Contracts and Contractor Personnel in Iraq and Afghanistan
Statement of John P.... |
Date March 25, 2009 |
Report No. GAO-09-342 |
Title
United States Government Accountability Office GAO
March 2009 Report to Congressional Requesters DEPARTMENT OF DEFENSE Additional Actions and Data Are Needed to Effectively Manage and Oversee DOD’s Acquisition Workforce GAO-09-342 March 2009 DEPARTMENT OF DEFENSE Highlights
Highlights of GAO-09-342, a report to congressional requesters Accountability Integrity Reliability Additional Actions and ... |
Date March 18, 2009 |
Report No. GAO-09-501T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:00 a.m. EDT Wednesday, March 18, 2000 Testimony Before the Committee on the Budget, House of Representatives DEFENSE ACQUISITIONS DOD Must Prioritize Its Weapon System Acquisitions and Balance Them with Available Resources
Statement of Statement of Michael J. Sullivan, Director Acquisition and Sourcing Manage... |
Date March 13, 2009 |
Report No. GAO-09-338 |
Title
United States Government Accountability Office GAO
March 2009 Report to Congressional Committees DEFENSE ACQUISITIONS Production and Fielding of Missile Defense Components Continue with Less Testing and Validation Than Planned GAO-09-338 March 2009 DEFENSE ACQUISITIONS Highlights
Highlights of GAO-09-338, a report to Congressional Committees Accountability Integrity Reliability Production and Fiel... |
Date March 12, 2009 |
Report No. GAO-09-303 |
Title
United States Government Accountability Office GAO
March 2009 Report to Congressional Committees JOINT STRIKE FIGHTER
Accelerating Procurement before Completing Development Increases the Government’s Financial Risk GAO-09-303 March 2009 JOINT STRIKE FIGHTER Highlights
Highlights of GAO-09-303, a report to congressional committees Accountability Integrity Reliability Accelerating Procurement befo... |
Date March 12, 2009 |
Report No. GAO-09-460T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:00 a.m. DST Thursday, March 12, 2009 Testimony Before the Committee on Armed Services, House of Representatives DOD’S HIGH-RISK AREAS Actions Needed to Reduce Vulnerabilities and Improve Business Outcomes
Statement of Gene L. Dodaro Acting Comptroller General of the United States GAO-09-460T March 12, 2009 ... |