Date |
Report No. |
Title |
Date Sept. 14, 2010 |
Report No. GAO-10-909 |
Title
United States Government Accountability Office GAO
September 2010 Report to Congressional Committees PUBLIC TRANSPORTATION Use of Contractors is Generally Enhancing Transit Project Oversight, and FTA is Taking Actions to Address Some Stakeholder Concerns GAO-10-909 September 2010 PUBLIC TRANSPORTATION
Accountability • Integrity • Reliability Use of Contractors is Generally Enhancing Transit Pr... |
Date Aug. 24, 2010 |
Report No. GAO-10-738 |
Title
United States Government Accountability Office GAO
August 2010 Report to the Ranking Member, Committee on Finance, U.S. Senate GROUP PURCHASING ORGANIZATIONS Services Provided to Customers and Initiatives Regarding Their Business Practices GAO-10-738 August 2010 Highlights
Highlights of GAO-10-738, a report to the Ranking Member, Committee on Finance, U.S. Senate Accountability Integrity Reliabili... |
Date Jan. 29, 2010 |
Report No. GAO-10-323R |
Title
United States Government Accountability Office Washington, DC 20548 January 29, 2010 The Honorable Charles E. Grassley Ranking Member Committee on Finance United States Senate Subject: Group Purchasing Organizations: Research on Their Pricing Impact on Health Care Providers Dear Senator Grassley: Hospitals and other health care providers use purchasing intermediaries—group purchasing organizatio... |
Date May 6, 1997 |
Report No. HEHS-97-71 |
Title
United States General Accounting Office GAO
May 1997 Report to the Chairman, Committee on Labor and Human Resources, U.S. Senate HEALTH INSURANCE Management Strategies Used by Large Employers to Control Costs GAO/HEHS-97-71 GAO United States General Accounting Office Washington, D.C. 20548 Health, Education, and Human Services Division B-271083 May 6, 1997 The Honorable James M. Jeffords Chairman,... |
Date May 9, 1996 |
Report No. GGD-96-108 |
Title
United States General Accounting Office GAO
May 1996 Report to the Chairman, Subcommittee on Oversight of Government Management and the District of Columbia, Committee on Governmental Affairs, U.S. Senate CONCESSIONS CONTRACTING DOD Military Exchange Services’ Rates of Return G A O years
1921 - 1996 GAO/GGD-96-108 GAO United States General Accounting Office Washington, D.C. 20548 General Governm... |
Date May 25, 1994 |
Report No. AIMD-94-88 |
Title
Little Progress Made in Resolving Important Issues c United States General Accounting Office Washington, D.C. 20648 Accounting and Information Management Division B-255794 May 25,1994 The Honorable John Conyers, Jr. Chairman The Honorable William F. Clinger, Jr. Ranking Minority Member Committee on Government Operations House of Representatives This report responds to your joint request and that o... |
Date April 22, 1993 |
Report No. T-IMTEC-93-5 |
Title
m .. * United StateaGeneral Ackmxdna Of&e r(t4oCY6 GAO Testimony
Beforethe Subcommittee Treasury, on PostalService,andGeneralGovernment Committeeon Appropriations Houseof Representatives
. FTS 2000 . Statusand Mandatory Use
Statement of JackL. Brock, Jr., hector Government Information andFiicial Management InformationManagement TechnologyDivision and . 149046 Mr. Chairman and Members of the Subcom... |
Date June 13, 1991 |
Report No. IMTEC-91-45 |
Title
III1--II_,I,.Y,,*I.-UI--i.l”~ l*-~.“l.l -l-.lll(~-l Iltlitwi States (&net-al Accounting Office GAO
.Jrtmh I!)91 &port, to the Chairman, Committee on Chwmunent Operations, House of IC~lprctsentat;ives TELECOMMUNICATIONS GSA’ Difficulties s Managing FTS 2000 (;AO/JM’ E(:-!)1-/3r, I‘ 4 6 !i I _-.~-- [Jni td St.a,t.es Gcttt~ral Accounting Office Report to the Chairman, Committee on Governmen... |
Date Sept. 28, 1990 |
Report No. NSIAD-90-290 |
Title
September 1990 CONTRACT PRICING Implementation of Cost Estimating Regulations
. ----- _L-_ GAO,‘NSLAD-90-290 : GAO United States General Accounting Office Washington, D.C. ‘20648 National Security and International Affairs Division B-241017.1 September 28, 1990 The Honorable John Conyers, Jr. Chairman, Legislation and National Security Subcommittee Committee on Government Operations House of R... |
Date April 4, 1990 |
Report No. IMTEC-90-45 |
Title
*. 2 ,I 1Jnited States General Accounting Office I &A0 Report to the Chairman, Committee on Government Operations, House of Representatives ’ ’ RETIREMENT SYSTEM Concerns About OPM’s FERS Automated Processing System Procurement
8 141179 t ‘GAO General Accounting Office Waehington, D.C. 20548 Information Management and Technology Division united states B-238930 April 4,199O The Honorable Jo... |
Date June 7, 1989 |
Report No. NSIAD-89-124 |
Title
*I IIIII~~1!M!) CONTRACT PRICING Overpricing of Secure Voice Communication Systems GeneralAccounting
washington, united state6
OfIke D.C. 20648 Intmnational Affair8 Division B-219741 June 7,1989 General A. G. Hansen Commander,U.S. Air Force Logistics Command Wright-Patterson Air Force Base,Ohio Dear General Hansen: As part of our continuing review of compliance with the Truth in Negotiations Act, ... |
Date May 12, 1988 |
Report No. GGD-88-65 |
Title
. United States Gemyal Accounting Office I WI 3 I ilr;ll a GAO
- . .I T 1leiss Report to CongressionalRequesters POSTAL PROCUREMENT: llllllll llllll ll
135785 H-2268 17 May 12,1988 The Honorable William D. Ford Chairman, Committee on Post Office and Civil Service House of Representatives The Honorable Frank McCloskey Chairman, Subcommittee on Postal Personnel and Modernization Committee on Post Of... |
Date Jan. 5, 1988 |
Report No. NSIAD-88-7 |
Title
^ 8,: ,‘ , 5 , LA!! United States General Accounting Office Report to the Chairman, Legislation and National Security Subcom m ittee, Com m ittee on Government Operations, House of Representatives
1988 January CONTRACT PRICING Defense Contractor Cost Estimating Systems United States General Accounting Office Washington, D.C. 20648 National Security and International Affairs Division B-219741 Jan... |
Date July 31, 1987 |
Report No. IMTEC-87-35 |
Title
8 .. . United States General Accounting Office Yo6Y. GAO
July 1987 Report to the Chairman, Committee on a Government Operations, House of Representatives ADP SYSTEM s Patent Office’ Contract Renegotiation Behind Schedule etEmT?ICTLQ - Mot to be released uulslde tha a;~!ncra~ approviai Accounting Office except on the basis ot specific &y$hc~ Qtfjctpfl fingr-s+nal Relr~onh~ IELEJ~SED GAO/‘ IMTEC... |
Date March 11, 1987 |
Report No. T-NSIAD-87-10 |
Title
,
-*.
l GAO United States General Accounting Office I3a 7dy Testimony For Release on Delivery Expected at 10:00 a.m. Wednesday March 11, 1987 STATE DEPARTMENT'S PROCUREMENT OF SILVERWARE FOR OVERSEAS MISSIONS Statement of Joan M. McCabe Associate Director, International Affairs Before the Legislation and National Committee on Government House of Representatives National Division Security and Secur... |
Date March 10, 1987 |
Report No. NSIAD-87-47 |
Title
, United Gltates General Accounting Office ’ ‘GAO
l%Iarch 1987 Report to the Chairman, Legislation and National Security Subcommittee, Committee on Government Ope:rations, Houseof Representatives il PROCUREMENT State Department’s Purchase of Silverware for OverseasMissions 132444 GAO/NSIAD-87-47 GAO United States General Accounting Office Washington, D.C. 20648 National Security and Internat... |
Date Dec. 3, 1986 |
Report No. T-NSIAD-87-1 |
Title
r IJNITED STATES GENERAL ACCOUNTING OFFICE
Testimonv For Release on Delivery Expected at The Air Force's C-5B Should Cost Study 10:00 a.m. EST Wednesday December 3, 1986 Statement of Paul F. Math, Associate Director National Security and International Affairs Division Before the Subcommittee on Oversight and Investigations Committee on Energy and Commerce House of Representatives GAO/T-NSIAD-87-1 ... |
Date Nov. 28, 1986 |
Report No. NSIAD-87-46 |
Title
United States General Accounting Office GAO
November 1986 13\709 Exposure Draft GOVERNMENT CONTRACTING A Proposal for A Program to Study the Profitability of Government Contractors 03~,Fjo,“I
GAO/NSIAD-87-46 Tentative for Discussion Only Preface Management information, based on accurate and current data, and sistent and impartial analysis is essential for efficient and effective eral program dec... |
Date Oct. 16, 1986 |
Report No. GGD-87-6FS |
Title
. United Gi!o St&es G&era1 Accounting Office 1 I Y 32 ‘,, Fact Sheet ‘for the Honorable Frank H. Mtirkowski, United States Senate W October 1986 PROFESSIONAL SERVICES, Federal Agencies’ Procurement of Professional Services From Alaskan Firms 131436 RESTRICmD---Not to be x+&wed outside the General Accounting Office except on the basis of specific RELEASED approortl by the C%floe of Congrtmion... |
Date Aug. 26, 1986 |
Report No. NSIAD-86-156 |
Title
c United States GWer& Accountin Office Report to the Commander,Aeronautical SystemsDivision Department of the Air Force
August 1986 CONTRACT PRICING Material Prices Overstated on T-56 Engine Contracts lull llllllllll
130804 GAO/NSIAD-86-166 * _-~-- GAO United Stated General Accounting Office _~-- Cincinnati Regional Office 8112 John Weld Peck Federal Building 5th & Main Streets Cincinnati, OH 4520... |
Date Oct. 3, 1985 |
Report No. 128052 |
Title
UNITED STATES GENERAL ACCOUNTING OFFICE WASHINtiTON, D.C. 20548 FOK RELEASE ON DELIVERY EXPECTED AT lo:00 A.M. THURSDAY, OCTOi3ER 3, 1985 STATEMENT OF FRANK C. CONAHAN, DIRECTOR NATIONAL SECURITY AND INTERNATIONAL AFFAIRS DIVISION dEFORE THE SUBCOMi~kITTEE LEGISLATION AND NATIONAL SECURITY ON OF THE COMMITTEE ON GOVERNMENT OPERATIONS UNITED STATES HOUSE OF REPRESENTATIVES ON GAO WORK AT DEFENSE CO... |
Date Feb. 14, 1985 |
Report No. NSIAD-85-31 |
Title
UN~TEDSTATESGENERALACCOUNTING OFFICE
WASHINGTON, D.C. 20548 NATIONAL INTERNATIONAL SECURITY AFFAIRS AND DIVISION B-217247 The Honorable Glenn English Chairman, Subcommittee on Government Information, Justice, and Agriculture Committee on Government Operations House of Representatives The Honorable Dennis DeConcini Ranking Minority Member Subcommittee on Treasury, Postal and General Government Comm... |
Date July 9, 1984 |
Report No. NSIAD-84-108 |
Title
l a I Q%+’ /gGQg , ‘ii? THEUS GENERALACCOUNTING OFFICE
Report To The Chairman, Subcommittee African Affairs Committee On Foreign Relations United States Senate On Direct Contracting By The Agency For :lnternational Development Can Be ‘Better Managed
~The Agency for lnternatronal Development )contracts wrth indrvrduals, educatronal instrtutrons, non-profit organrzatrons, and private firms to ... |
Date Sept. 20, 1983 |
Report No. NSIAD-83-33 |
Title
UNITED STATES GENERAL ACCOUNTINGOFFICE
WASHINGTON, D.C. 20548 B-211827 SEPTEMBER 20.1983 The Honorable Administrator Harry N. Walters of Veterans Affairs Dear Mr. Walters:
Subject: Better Management and Price Negotiation Will Improve the Veterans Administration's Multiple Award Schedule Program (GAO/NSIAD-83-33) We reviewed the Veterans Administration's (VA's) procurement of drugs and pharmaceutic... |
Date Aug. 31, 1983 |
Report No. HRD-83-79 |
Title
UNITEDSTATES GEYFR~LACCOWTIM OFFICE
WASHINGTON, D G 20543 HUHAN RESOURCES DIVISIOI* Augvst 31 , 1383 B-205028 The Honorable Unlted States Howard Senate H. Baker, Duncan Jr. The Honorable John J. House of Representatives RELEASED The Honorable James H. Qulllen House of Representatives Sublect: 1 Review of Contract Award for National Center for Research Education (GAO/HRD-83-79) Yanagement of In Voc... |
Date Aug. 31, 1983 |
Report No. HRD-83-69 |
Title
COMPTROLLER GENERAL
WASHINGTON OF
DC THE
to548 UN ITED STATES B-210338 AUGUST 31,1983 The Honorable Robert W. Kastenmeler Chairman, Subcommittee on Courts, Civil Liberties, and the Administration of Justice Committee on the Judiciary House of Representatives The Honorable United States The Honorable Unlted States Sublect: Edward Senate Lowell Senate M. Kennedy P. Welcker, Jr. of and the The Legal ... |
Date Aug. 8, 1983 |
Report No. NSIAD-83-29 |
Title
UNITED STATES GENERAL ACCOUNTING OFFICE WASHINGTON, DC 20548 x-445 NATIONAL INTERNATIONAL SECURITY AFFAIRS AND DIVISION 0 8 AUG1983 Vice Admiral E. A. GrInstead, SC, USN Director, Defense Logistics Aqency Cameron Station Alexandria, Virginia 22314 Dear Admiral Sublect: Grinstead: Contract Pricing in the Meals-Ready-To-Eat Program (GAO/NSIAD-83-29) We have examined the pricing of contract DLA 13H-7... |
Date July 29, 1983 |
Report No. NSIAD-83-1 |
Title
UNITEDS~ATESGENERALACCOUNTING OFFICE
WASHINGTON. D.C. 20548 B-211991 The Honorable Edwin B. Forsythe Ranking Minority Member Committee on Merchant Marine and Fisheries House of Representatives Dear
Mr. JULY 29.1983 Forsythe: Panama Canal Commission Procurement Contracting (GAO/NSIAD-83-l) and Subject: This report is in adequacy of the Panama goods and services and Details are discussed response to... |
Date March 8, 1983 |
Report No. PLRD-83-49 |
Title
di I
UNITED STATES GENERAL AC~UNTING
WASHINGTON, DC. 20548 cat7kylrti;fOFFICE /zlOs% PROCUHEMENT,
AND READINESS LOGISTICS, DIVISION B-210718 RELEASED MARCH 8,1983 The Honorable Carl Levin Committee on Armed Services United States Senate near Senator Subject: Levin:
121038 Followup on the December 1981 Dollar Threshold Change for Certified Cost or Pricing Data,,, :(GAO/PLRD-83-49) ,,,,, ,, This rep... |
Date Nov. 12, 1982 |
Report No. PLRD-83-14 |
Title
,I .I” : I c 1 : 1 . 1 i) 1’ c. 7, * I , 1
I UNITED STATES GENERAL
REGIONAL A,CCOUhiTlNG OFFICE
OFFICE f3uilcfktq Room 1992, Federal Seattle, Washington 98174 hov 1 2 1882
Mr. Stephen J. Rail, Regional Small Business Administration 710 Second Avenue Seattle, Washington 98104 Dear Mr. Hall: Administrator 119987 IllI Subject: Division of Responsibilities Betwcren SBA and ?rocurin&Igencies in Ev,... |
Date Sept. 10, 1982 |
Report No. PLRD-82-114 |
Title
UNITED STATES GENERAL ACCOUNTING OFFICE
WASHINGTON, D.C. 20548 PROCUREMENT, AN0 READINESS LOGISTICS, DIVISION B-207486 The Honorable John Tower Chairman, Committee on Armed Services United States Senate Dear Mr. Chairman: Subject: SEPTEMBER 10.1982 Sale of Industrial Assets Owned by the Department of Defense (GAO/PLRD-82-114) In your April 13, 1982, letter, you asked us to review the General Servi... |
Date Aug. 30, 1982 |
Report No. PLRD-82-118 |
Title
STATES GENERAL ACCOUNTING OFFICE
WASHINGTON, D.C. 20548 B-208565 AUGUST 3iI,lQ82 The Honorable United States Dear Senator Subject: John G. Tower Senate Tower: Federal Government's Use of International Corporation's Subscription Services (GAO/PLRD-82-118) Data This is in response to your October 23, 1981, letter concerning the Federal Government's procurement of automatic data processing (ADP) info... |
Date March 24, 1982 |
Report No. PLRD-82-51 |
Title
4 -4 *I ” . )I , a9 ’ 1 +j~/~;;-~j ‘ “ . ’ I, BiTHE US GENERALACCOUNTING OFFICE *- Report To The Secretaries O f defense And Energy And To ihe Administrator O f NASA
Agency Implementation O f Cost Accounting Standards: Generally Good But More Training Needed
before it ceased operations in 1980, the Cost Accounting Standards Board issued 19 standprds for cost accounting on negotiated defe... |
Date March 10, 1982 |
Report No. PLRD-82-50 |
Title
UNITED STATES GENERAL ACCOUNTINGOFFICE
WASHINGTON, D.C. 20548 /206/8 Col. A. R. Burke , Commander DELHD-CO Harry Diamond Laboratories 2800 Powder Mill Road Adelphia, Maryland 20783 Dear Colonel Subject: Burke: 120618 I
Cost of (PLRD 82-50) Improvements Needed in Evaluation of Proposals and Technical Administration Management Support Services Contracts I This report summarizes our limited review of... |
Date March 10, 1982 |
Report No. GGD-82-45 |
Title
h UN~T~ATES GENERALACCOUNTING
WASHINGTON, D.C. 29548 OILNERIL, QOVLRNMISNT OIVISlON B-114874 MARCH lo,1982 The Honorable S. William House of Representatives Dear Mr. Green: Subject: Green Stamp Collecting
The U.S. Postal Kits Bought By Service: (GGD-82-45) Your March 23, 1981, letter requested GAO to investigate certain aspects of how the Postal Service solicits and awards contracts for stamp coll... |
Date Feb. 24, 1982 |
Report No. PLRD-82-36 |
Title
, c BY THEU.S.GENERALACCOUNTING dFFlCE Report To The Administrator Of General Services GSA Nonstores Procurement Program Falls Far Short Of Its Objectives
The GSA nonstores program is a conglomeration of procurement activities designed to provide Federal agencies with a wide variety of items not generally available through other major GSA procurement programs. However, weaknesses in the program’... |
Date Jan. 25, 1982 |
Report No. 117380 |
Title
UNITED STATESGENEIW ACCNINTING OFFICE
REGIONAL OFFICk SUITR 8ood, 2420w. 26Tl-l AVENUE DENVER, COLORADO 80211
‘! Mr. Don W. Minnich Regional Director Fish and Wildlife Service P.O. Box 25486 Denver Federal Center Denver, Colorado 80225 Dear Mr. Minnich: We have completed an examination of procurement practices and procedures used by selected Denver-area Department of the Interior'bureaus. and ef... |
Date Oct. 20, 1981 |
Report No. 116663 |
Title
UNITED STATES GENERAL ACCOUNTINGOFFICE WASHINGTON, D.C.
20548 FOR RELEASE ON DELIVERY Expected at 9:00 a.m., EDT Tuesday,' October 20, 1981 STATEMENTOF GREGORY AHART, DIRECTOR J.
HUMAN R;SSDI.,RCES DIVISION GENERAL ACCOUNTINGOFFIC3 BEFORE THE SENATE COMMITTEEON LABOR AND HUMA RESOURCES ON DEPARTMENT LABOR'S OF OFFICE OF NATIONAL PROGRAMS'ADMINISTRATION OF EMPLOYMENT AND TRAINING AWARDS Mlllll Ill ... |
Date Sept. 11, 1981 |
Report No. 116595 |
Title
UNITED STATES GENERAL ACCOUNTING OFFICE
REGIONAL OFFICE
SUITE 300-D, 2420 W. 26TH AVENUE DENVER, COLORADO 80211 Step i I98i Hr. Ton Coston, Regional Forester U.S. Forest Service P.O. Box 7669 Miissoula, Hlontana 59807 Dear fir. Coston: Ile have completed an examination of procurement practices and procedures used by the 1lissoula Regional and Flathead National Forest Offices in awarding contracts.... |
Date June 10, 1981 |
Report No. HRD-81-100 |
Title
c c J UNITED STATES GENERAL ACCOUNTINGOFFICE
WASHINGTON, D.C. 20548 HUMAN RESOURCES DIVISION RELEASED JUNE 10.1981 Dear Senator Subject: Melcher: -7 Process Used by tGi& Department of Education 1. to Award Contracts for Operation of Indian Education Resource and Evaluation Centers (~~~-81-100) J you asked us to review and In your March 27, 1981, letter rank the contract proposals received by the D... |
Date April 27, 1981 |
Report No. 115034 |
Title
United
/ States General Accounting Office Washington, D. C. 20548 FOR RELEASE ON DELIVERY Monday, April 27, 1981 STATEMENTOF SEYMOUREFROS ASSOCIATE GENERAL COUNSEL BEFORE THE I SENATE COMMITTEE ON SMALL BUSINESS ON ?---LSMALL BUSINESS ADMINISTRATION CONTRACTING PRACTICES Mr. Chairman to be here requirements today for and Members of the Committee, to assist competition knowledge actions you . your ... |
Date March 5, 1981 |
Report No. MASAD-81-16 |
Title
UNITED STATES GENERAL ACCOUNTING OFFICE
WASHINGTON, D.C. 20548 MISSION SYSTEMS ANALYSIS ACQUlSlTlON AND OlVlSlON MARCH 5,198l a-202293 The Honorable The Secretary
Subject: Drew L. Lewis of Transportation
E- 114504 ontract Overpriced and Established Regulations and Procedures t?ot (NASAD-81-16) Dear Nr . Secretary: In reviewing the pricing of firm-fixed-price contract DOT-FA77tiA-4047, we found tha... |
Date Feb. 28, 1981 |
Report No. MASAD-81-11 |
Title
BY THECOMPTROLLERGENERAL’ OF THEUNITED STATES ,I/ -- Report ToThe Congress
Air Force And Navy Plans To Acquire Trainer Aircraft
The Air Force and Navy plan to acquire four different aircraft for training missions. Total costs are expected to be several billion dollars. With one exception, the Air Force Next Generatijon Trainer and the Navy Undergraduate Jet Flight Training System acquisition pro... |
Date Nov. 1, 1980 |
Report No. 088867 |
Title
Government Contract
Principles GOVERNMENT CONTRACT P R I X I P L E S THIRD E D I T I O N Canpiled in the Office of the General Counsel U. S. General Accounting Office i November 1980 For male by the Hiiperlaterrdrat ot Docurnrats. E.8.Oorcromcnt Prhtlng omce
Waublnctoa. U C 20.102 .. FOREWORD This c o n t r a c t manual is intended for use as a g e n e r a l i n t r o d u c t i o n t o Government ... |
Date Oct. 17, 1980 |
Report No. PSAD-81-3 |
Title
B)’ THE U.S.GENERALACCOUNTING OFFICE I , \ (3J7b Report To The Secretary Of Defense
I R+view Of lected Negotiated Contracts Under e F-16 Multinational Aircraft Program
over 99 percent of 20 negotiated t actions, valued at about $3 bilreasonably priced. GAO believes ion of this amount is potentially overue to ineffective use of available data; upon inaccurate, incomplete, or nondata; and poor pro... |
Date Feb. 20, 1980 |
Report No. 094391 |
Title
. L 1;“ I OWYI
STANDARDS BOARD ()fl&, .* , ELMER B. STAATS, CHAIRM:;?$;;O"NTING LEGISLATIVE SUBCOMMITTEE OF THE APPROPRIATIONS COMMITTEE U,S. HOUSE OF REPRESENTATIVES COST ACCOUNTIN:NSTANDARDS BOARD BUDGET ESTIMATES FOR FISCAL YEAR 1981 MR. CHAIRMAN AND MEMBERSOF THE SUBCOMMITTEE: I am appearing Cost Accounting Board operations Our budget is $339,000 describing review less before you today in my... |
Date Nov. 2, 1979 |
Report No. 094303 |
Title
a STATEMENT OF . ELMER 6. STAATS, CHAIRMAN COST ACCOUNTING STANDARDS BOARD BEFORE THE UNITED STATES SENATE COMMITTEE ON BANKING, HOUSING AND URBAN AFFIARS .:“'e ) I am appearing Cost States personnel, General The Branch with Accounting in support and Accounting House here today Board in the dual capacity of Chairman of the of United the Standards of records and Comptroller to Cost transfer Accou... |
Date Oct. 24, 1979 |
Report No. PSAD-80-4 |
Title
s. 1110 ??
D.C. 20548 UNITED STATES GENERAL ACCOUNTING OFFICE
WASHINGTON, PROCUREMENT AND SYSTEMS ACQUISITION DIVISION B-168450 The Honorable Harold Brown The Secretary of Defense Attention: f OCTOBER 24, 1979 IgI
110662 Assistant for Audit Reports Room 3A336 ASD (Comptroller) Dear Mr. Secretary: Subject: The ir Force Should Recover Excess Costs of Prior F-15 Contracts and Take Action to Save Cost... |
Date Oct. 10, 1979 |
Report No. 110553 |
Title
UNITED STATES GENERALACCOUNTING OFFICE WASHINGTON,D.C. 20548 FOR RELEASEON DELXVERY Expected at 9:3Q a.m. Wednesday, October 10, 1979 STATEMENTOF DONALDL. SCANTLEBURY DIRECTOR, FINANCIAL AND GENERAL MANAGEMENT STUDIES DIVISION . BEFORETHE SUBCOMMITTEE LEGISLATION AND NATIONAL SECirRITY ON COMMITTEEON GOVERNMENT OPERATIONS HOUSEOF REPRESENTATIVES
ON IR FORCE "PHASE IV" COMPUTER SYSTEMACQUISITION PR... |
Date Aug. 21, 1979 |
Report No. PSAD-79-93 |
Title
, I
~Mi10172 tlaElz BY THECOMPTROLLERGiNERAL OF THEUNITEDSTATES llIlllllllllllllllIll11 lllll lllllIll11 Ill IllI IllI ngress
Civil Agencies Can Do A Better tiating Noncompetitive cil Qver $lQO,OOO
Federal civil agencies are negotiating noncompetitive contracts without adequate information. They do not always obtain enough cost or pricing data on contractors’ proposed prices, properly analyze it... |