Date Oct. 7, 2010 |
Report No. GAO-11-100 |
Title
United States Government Accountability Office GAO
October 2010 Report to the Subcommittee on Strategic Forces, Committee on Armed Services, House of Representatives NUCLEAR WEAPONS National Nuclear Security Administration Needs to Ensure Continued Availability of Tritium for the Weapons Stockpile GAO-11-100 October 2010 Highlights
Highlights of GAO-11-100, a report to the Subcommittee on Strategi... |
Date April 8, 2010 |
Report No. GAO-10-488 |
Title
United States Government Accountability Office GAO
April 2010 Report to the Subcommittee on Energy and Water Development, Committee on Appropriations, U.S. Senate NUCLEAR WEAPONS Actions Needed to Address Scientific and Technical Challenges and Management Weaknesses at the National Ignition Facility GAO-10-488 April 2010 NUCLEAR WEAPONS Highlights
Highlights of GAO-10-488, a report to the Subcommi... |
Date March 2, 2009 |
Report No. GAO-09-385 |
Title
United States Government Accountability Office GAO
March 2009 Report to the Subcommittee on Strategic Forces, Committee on Armed Services, House of Representatives NUCLEAR WEAPONS NNSA and DOD Need to More Effectively Manage the Stockpile Life Extension Program GAO-09-385 March 2009 NUCLEAR WEAPONS Highlights
Highlights of GAO-09-385, a report to the Subcommittee on Strategic Forces, Committee on ... |
Date July 25, 2008 |
Report No. GAO-08-840 |
Title
United States Government Accountability Office GAO
July 2008 Report to the Subcommittee on Energy and Water Development, Committee on Appropriations, House of Representatives NUCLEAR MATERIAL DOE Needs to Take Action to Reduce Risks Before Processing Additional Nuclear Material at the Savannah River Site’s H-Canyon GAO-08-840 July 2008 NUCLEAR MATERIAL Highlights
Highlights of GAO-08-840, a repo... |
Date July 17, 2008 |
Report No. GAO-08-1032T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:00 a.m. EDT Thursday, July 17, 2008 Testimony Before the Subcommittee on Strategic Forces, Committee on Armed Services, House of Representatives NUCLEAR WEAPONS Views on NNSA’s Proposal to Transform the Nuclear Weapons Complex
Statement of Gene Aloise, Director Natural Resources and Environment GAO-08-1032T... |
Date Jan. 10, 2008 |
Report No. GAO-08-173R |
Title
DRAFT United States Government Accountability Office Washington, DC 20548 January 10, 2008 The Honorable Peter J. Visclosky Chairman The Honorable David L. Hobson Ranking Member Subcommittee on Energy and Water Development Committee on Appropriations House of Representatives Subject: Los Alamos National Laboratory: Information on Security of Classified Data, Nuclear Material Controls, Nuclear and ... |
Date April 26, 2006 |
Report No. GAO-06-606T |
Title
United States Government Accountability Office GAO
For Release on Delivery Expected at 10:00 a.m. EDT Wednesday, April 26, 2006 Testimony Before the Subcommittee on Energy and Water Development, Committee on Appropriations, House of Representatives NUCLEAR WEAPONS Views on Proposals to Transform the Nuclear Weapons Complex
Statement of Gene Aloise, Director Natural Resources and Environment GAO-06... |
Date Nov. 18, 2005 |
Report No. GAO-06-83 |
Title
United States Government Accountability Office GAO
November 2005 Report to the Chairman, Committee on Energy and Commerce, House of Representatives STAND-DOWN OF LOS ALAMOS NATIONAL LABORATORY Total Costs Uncertain; Almost All Mission-Critical Programs Were Affected but Have Recovered GAO-06-83 a November 2005 Highlights
Highlights of GAO-06-83, a report to the Chairman, Committee on Energy and Co... |
Date Nov. 21, 2003 |
Report No. GAO-04-249T |
Title
United States General Accounting Office GAO
For Release on Delivery Expected at 9:30 a.m. EST Friday, November 21, 2003 Testimony Before the Committee on Energy and Natural Resources, U.S. Senate ENERGY EMPLOYEES COMPENSATION Case-Processing Bottlenecks Delay Payment of Claims
Statement of Robert E. Robertson, Director, Education, Workforce, and Income Security Issues GAO-04-249T November 2003 ENE... |
Date Jan. 28, 2000 |
Report No. RCED-00-24 |
Title
United States General Accounting Office GAO
January 2000 Report to the Chairman, Committee on Armed Services, U.S. Senate NUCLEAR WEAPONS Challenges Remain for Successful Implementation of DOE’s Tritium Supply Decision GAO/RCED-00-24 Contents Letter Appendixes
Appendix I: Total Life-Cycle Cost Estimates for the Reactor and Accelerator Program Scenarios for Producing Tritium Appendix II: Scope an... |
Date Nov. 9, 1998 |
Report No. RCED-99-1 |
Title
United States General Accounting Office GAO
November 1998 Report to the Committee on Armed Services, U.S. Senate NUCLEAR WEAPONS Key Nuclear Weapons Component Issues Are Unresolved GAO/RCED-99-1 GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic Development Division B-280854 November 9, 1998 The Honorable Strom Thurmond Chairman The Honorable Carl... |
Date March 31, 1998 |
Report No. RCED-98-75 |
Title
United States General Accounting Office GAO
March 1998 Report to the Committee on Armed Services, U.S. Senate NUCLEAR WEAPONS Design Reviews of DOE’s Tritium Extraction Facility GAO/RCED-98-75 GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic Development Division B-279101 March 31, 1998 The Honorable Strom Thurmond Chairman The Honorable Carl L... |
Date Feb. 20, 1998 |
Report No. NSIAD-98-78R |
Title
3!0 United States General Accounting Qf6ce Washington, D.C. 20548 National Security and h#mmational Affairs Division B-279066 February 20,1998 The Honorable Floyd Spence Chairman, Committee on National Security House of Representatives Subject: fluclear Weanons: U.S. Cooueration With Other Countries Dear Mr. Chairman In light of the pending ratlflcation debate on the Comprehensive Test Ran Treaty ... |
Date April 25, 1997 |
Report No. RCED-97-128R |
Title
United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic Development Division B-276642 April 25, 1997 The Honorable Floyd D. Spence Chairman The Honorable Ronald V. Dellums Ranking Minority Member Committee on National Security House of Representatives Subject: Detxrtment of Enerm: Information on the Distribution of Funds for Counterintelligence Programs an... |
Date April 15, 1997 |
Report No. T-NSIAD-97-128 |
Title
United States General Accounting Office GAO
For Release on Delivery Expected at 2:00 p.m., EST Tuesday, April 15, 1997 Testimony
Before the Subcommittee on Military Procurement, Committee on National Security, House of Representatives EXPORT CONTROLS Sales of High Performance Computers to Russia’s Nuclear Weapons Laboratories
Statement of Mr. Harold J. Johnson, Associate Director, International ... |
Date March 5, 1997 |
Report No. RCED-97-52 |
Title
United States General Accounting Office GAO
March 1997 Report to the Committee on Armed Services, U.S. Senate NUCLEAR WEAPONS Capabilities of DOE’s Limited Life Component Program to Meet Operational Needs GAO/RCED-97-52 GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic Development Division B-276096 March 5, 1997 The Honorable Strom Thurmond Cha... |
Date May 23, 1996 |
Report No. RCED-96-124 |
Title
United States General Accounting Office GAO
May 1996 Report to the Chairman, Subcommittee on Military Procurement, Committee on National Security, House of Representatives NUCLEAR WASTE Greater Use of Removal Actions Could Cut Time and Cost for Cleanups G A O years
1921 - 1996 GAO/RCED-96-124 GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic Deve... |
Date March 21, 1996 |
Report No. T-RCED/NSIAD-96-127 |
Title
United States General Accounting Office GAO
For Release on Delivery Expected at 2:00 p.m. EST Thursday March 21, 1996 Testimony
Before the Subcommittees on Military Procurement and Military Readiness, Committee on National Security, House of Representatives ENVIRONMENTAL PROTECTION Issues Facing the Energy and Defense Environmental Management Programs
Statement of Victor S. Rezendes, Director, Ene... |
Date March 13, 1996 |
Report No. T-RCED-96-100 |
Title
United States General Accounting Office GAO
For Release on Delivery Expected at 9:30 a.m. EST Wednesday, March 13, 1996 Testimony
Before the Subcommittee on Strategic Forces, Committee on Armed Services, United States Senate NUCLEAR WEAPONS Status of DOE’s Nuclear Stockpile Surveillance Program
Statement of Victor S. Rezendes, Director, Energy, Resources, and Science Issues Resources, Community,... |
Date Dec. 27, 1995 |
Report No. RCED-96-36 |
Title
United States General Accounting Office GAO
December 1995 Report to the Secretary of Energy ENERGY DOWNSIZING Criteria for Community Assistance Needed GAO/RCED-96-36 GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic Development Division B-270358 December 27, 1995 The Honorable Hazel R. O’Leary The Secretary of Energy Dear Madam Secretary: Since... |
Date May 8, 1995 |
Report No. RCED-95-118 |
Title
United States General Accounting Office GAO
May 1995 Report to the Ranking Minority Member, Committee on Commerce, House of Representatives NUCLEAR FACILITY CLEANUP Centralized Contracting of Laboratory Analysis Would Produce Budgetary Savings GAO/RCED-95-118 GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic Development Division B-260566 May 8, 1... |
Date March 6, 1995 |
Report No. T-RCED-95-120 |
Title
United States General Accounting Of&e -= GAO Testimony
Before the Committee on Energy and Natural Resources U.S. Senate For Release Delivery on Expectedat 2:OO p.m. EST Monday March 61995 NUCLEAR WEAPONS COMF’ LEX Establishing a National Risk-Based Strategy for Cleanup
Statement of Bemice Steinhardt, Associate Director, Energy and Science Issues, Resources, Community, and Economic Development Di... |
Date March 3, 1995 |
Report No. RCED-95-1 |
Title
United States General Accounting Office GAO
March 1995 Report to the Secretary of Energy DEPARTMENT OF ENERGY National Priorities Needed for Meeting Environmental Agreements GAO/RCED-95-1 GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, and Economic Development Division B-256136 March 3, 1995 The Honorable Hazel R. O’Leary The Secretary of Energy Dear Mada... |
Date Dec. 29, 1994 |
Report No. RCED-95-49 |
Title
. I at United States General Accounting Office Washington, D.C. 20648 Resources, Community, Economic Development and Division December 29,1994 The Honorable John D. Dingell Chairman, Subcommittee on Oversight and Investigations Committee on Energy and Commerce House of Representatives Dear Mr. Chairman: Since the 196Os,the Department of Energy’ (DOE) Rocky Flats Plant has s processed material co... |
Date April 7, 1994 |
Report No. RCED-94-154FS |
Title
United States General Accounting Office GAO
A@ 1994 Report to the Chairman, Environment, Energy, and Natural Resources Subcommittee, Committee on Government Operations, House of Representatives DEPARTMENT OF, 10. ENERGY Status of DOE’ s Property Management Program GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, Economic Development and
Division B-256705 A... |
Date March 1, 1994 |
Report No. RCED-94-77 |
Title
GAO United States General Accounting Office Washington, D.C. 20548 /Sd?OZ Resources, Community, Economic Development and Division B-255689
March 1,1994 The Honorable Mike Synar Chairman, Environment, Energy, and Natural Resources Subcommittee Committee on Government Operations House of Representatives The Honorable David E. Skaggs House of Representatives The Honorable Ben Nighthorse Campbell Uni... |
Date Dec. 1, 1993 |
Report No. T-RCED-94-86 |
Title
United States General Accounting Office GAO
For Releaseon Delivery Expectedat 1OAHI EST am. Wednesday Dec. 1.1993 Testimony
Before the Subcommittee on Oversight and Investigations Committee on Energy and Commerce House of Representatives DOE MANAGEMENT Implementing the Environmental Restoration Management Contractor Concept
Statementof Victor S. Rezendes, Director, Energy and Science Issues, Resou... |
Date Oct. 27, 1993 |
Report No. RCED-94-49R |
Title
GAO United States General Accounting Office Washington, D.C. 20548 Resources, Community, Economic Development and Division B-249446 October 27, 1993 The Honorable John D. Dingell Chairman, Subcommittee on Oversight and Investigations Committee on Energy and Commerce House of Representatives Dear Mr. Chairman: You requested that we determine how the Department of Energy (DOE) has implemented our re... |
Date Aug. 17, 1993 |
Report No. RCED-93-189 |
Title
NUCLEAR MAITERIALS Nuclear Arsenal Reductions Allow Consideration of Tritium Production Options j~l :) Id rmt ql\I,-!t:3-18!) ..--- RESTRICTED--IX% to be released outside the General Accoux$& Office unless specifically approved by th!g Office of Congressional Relations. c‘ 4 mw9 ,. RELEASED GAO United States General Accounting Oface Washington, D.C. 20648 Resources, Community, Economic Developme... |
Date March 4, 1993 |
Report No. RCED-93-71 |
Title
I Ilkit ccl St.;tt.w Gerleral Awonnt,ing Offiw * GAO
Kwt, I!W~ Report t;o the Chairman, Cornmit;t;et? on Governmental Affairs, U.S. Senate NUCLEAR WASTE Hanford’s Well-Drilling Costs Can Be Reduced II ll. lllllllllll
148866 RESTRICTED--Not to be released outside the General Accounting Office unless specifically approved by the Office of Congressional Relations. ’ 556565 RELEASED United States ... |
Date Nov. 19, 1992 |
Report No. RCED-93-56 |
Title
Unlltzd Sta4qs C+qkd Aqmuntiag OffIce I&port to Congressicmd Requesters November 1992 ;AO/lWED-93-56 GAO United States General Accounting Office Washington, D.C. 20648 Resources, Community, and Economic Development Division
B-250995 November 19,199Z The Honorable John Glenn Chairman, Committee on Governmental Affairs United States Senate The Honorable Timothy E. Wirth United States Senate The Hono... |
Date Oct. 16, 1992 |
Report No. RCED-93-32 |
Title
I Jnitcd States Getlc:ml Accomting Office Report t;o Congressional Requesters DEPARTMENT OF ENERGY Project Management at the Rocky Flats Plant Needs Improvement lllllllll~llll ll
147973 RESTRICTED--Not to be released outside the General Accounting Office unless specifically approved by the Office of Congressional Relations. 5sS783 RELEASED GAO United State@ General Accounting OffIce Washington, D.... |
Date Sept. 4, 1992 |
Report No. RCED-92-219 |
Title
* United States General Accounting Office GAO
September 1992 Report to Congressional Requesters NUCLEAR MATERIALS Removing Plutonium Residues From Rocky Flats WrlllBe Difficult and Costly :. -. >’ -; , RESTRICTED--Not to be released outside the General Accounting Office unless specifically approved by the Office of Congressional Relations. 55-5-30,._ --2&~~AS~~ 7- .-.. Resources, Community, Econ... |
Date Aug. 20, 1992 |
Report No. RCED-92-109FS |
Title
GAO NUCLEAR MXYTERIALS I” %‘actSheet for the Chairman, I Environment, Energy, and Natural Resources Subcommittee, Committee on j Government Operations, House of Representatives -. ._. .--.-.-.--- -.-.-.--.....__.-.._ ._.- .__ .-.-. -..--..-^. ..--...._ _... __..-- ...- .___I_ -,_ ...._-_.. .-. tJniteci Stats t’; |
Date Aug. 14, 1992 |
Report No. RCED-92-244 |
Title
[.nitctd Stat.es General Accounting Office GAO Report to the Chairman, Subcommittee on Oversight and Investigations, Committee on Energy and Commerce, House of Representatives DOE MANAGEMENT Impediments to Environmental Restoration Management Contracting
--_ ill111111 Ill ll
147428 ----I- _. _.~ ..___ ____ ,..,.... -., .._"_,
Gfi()/Ii |
Date June 22, 1992 |
Report No. RCED-92-176FS |
Title
(Jnitd States General Accounting Office GAO Fact Sheet for Congressional Requesters _--------_- NUCLEAR mAPONS COMPLEX Status of Restart Issues at the Rocky Flats Plant
147138 RESTRICTED--Not to be released outside the General Accounting Office unless specifically approved by the Offke of Congressional Relations.
._-_._._ --_ ...“-.~.- ^._...I 354-m GAOLRCED-92-176FS GAO United Statee General Ac... |
Date April 10, 1992 |
Report No. RCED-92-145 |
Title
IJnited. States_..General Accounting ---. _._ .__ .._.__.--_-.. Offlce _---_---.- --- ..I--. Report to Congressional Requesters .__..--- April 1992 CLEANUP TECHNOLOGY Better Management for DOE’ Technology s Development Program
, 146565 1111111 ll RESTRICTED--Not to be released outside the General Accounting Office unless specifically approved by the Office of Congressional Relations. RELEASED
,,... |
Date April 9, 1992 |
Report No. RCED-92-121FS |
Title
GAO
NUCLEAR SCIENCE Fast Flux Test Facility on Standby, Awaiting DOE Decision on Future Missions
146564 RESTRICTED--Not to be released outside the General Accounting Office unless specifically approved by the Office of Congressional Relations. (;Ao/H( .-.-.--~;;IBld.BlW :1~1)-!)2-12 1 I’ S ___--_.- ------. .-.----. -. GAO General Accounting Odnce Washington, D.C. 20548 Resources, Community, and ... |
Date April 1, 1992 |
Report No. T-RCED-92-49 |
Title
United States General Accounting Off’ke GAO
For Releaseon Delivery Expectedat 9:30 a.m. EST Wednesday April I,1992 Testimony
Before the Department of Energy DefenseNuclear Facilities Panel Committee on Armed Services House of Representatives NUCLEAR WEAPONS COMPLEX GAO’s Views on Reconfiguring the Complex
Statementof Victor S. Rezendes, Director, Energy Issues Resources,Community, and Economic... |
Date March 30, 1992 |
Report No. T-RCED-92-43 |
Title
United StatesGeneralAccounting Office / /&db / GAO
For Releaseon Delivery Expectedat I:00 p.m., EST Monday March 30, 1992 Testimony
Before the Department of Energy Defense Nuclear Facilities Panel Committee on Armed Services House of Representatives Ill II llwllll
146265 NUCLEAR WEAPONS COMPLEX Improving DOE’ s Managementof the Environmental Cleanup
Statement of Victor S. Rezendes,Director, Ener... |
Date March 24, 1992 |
Report No. RCED-92-162 |
Title
-- -- March 1!)!U NUCLEAR HEALTH AND SAFETY Increased Rating Results in Awaxd Fee to Rocky Flats Contractor
. -, : i.--“-.-- ’ (;Aolfil(:I:I)-!)2-162
, -‘ a United Statee General Accounting Odlice Washington, D.C. 20648 Besources, Community, and Economic Development Division B-234139 March 24,1992 The Honorable Timothy E. Wirth United States Senate The Honorable David I$. Skaggs House of Rep... |
Date Feb. 26, 1992 |
Report No. T-RCED-92-29 |
Title
United States General Accounting Office GAO
For Releaseon Delivery Expected at 1:30 p.m., EST February 26.1992 Testimony
Beforethe Subcommittee Environment,Committeeon on Science, Space, Technology and Houseof Representatives CLEANUPTECHNOLOGY DOE's Managementof
Environmental Cleanup Technology
Statement Victor S. Rezendes, of Director, EnergyIssues, Resources, Community,andEconomicDevelopment Div... |
Date Feb. 25, 1992 |
Report No. T-RCED-92-31 |
Title
United States General Accounting Office Testimony
Before the Committee on Governmental Afkirs, U.S. Senate For Releaseon Delivery Expectedat 9:30 a.m., EST Tuesday February 251992 NUCLEAR WEAPONS COMPLEX Major Safety, Environmental, and Reconfiguration Issues Facing DOE
Statementof J. Dexter Peach,Assistant Comptroller General, Resources,Community, and Economic Development Division GAO/T-RCED-92-3... |
Date Dec. 13, 1991 |
Report No. RCED-92-39 |
Title
GAO tCc:poy’t the Chairman, Subconunittee to on Oversight and Investigations, Ck mmnittee on Energy and Commerce, Hoarseof Representatives NUCLEAR SECUlRITY Safeguards and Security Weaknesses at DOE’s Weapons Facilities ,“,,. ~1,1 _*._. “.__” ..- “,.l,--.ll..l _“~ ,.__ “-.l _,,., ““, .“. .“..“* I_ lll_...-l_(-ll- _.” ._.-...““.- ..-. *-.. “.. ---_ -.... _ -_111 I.... |
Date Oct. 31, 1991 |
Report No. RCED-92-1 |
Title
GAO NUCLEAR SCIENCE Accelerator Technology for Tritium Production Needs Further Study ,I “...” -I _ -.. -..-__.- _-------~.---..__.. -_--- GAO United States General Accounting Office Washington, D.C. 20648 Resources, Community, Economic Development and Division B-231 142 October 31,lQQl The Honorable Brock Adams United States Senate Dear Senator Adams: In your February 7, 1990, letter you expr... |
Date Sept. 10, 1991 |
Report No. RCED-91-203 |
Title
GAO United States General Accounting Office Washington, D.C. 20648 Resources, Community, Economic Development and Division B-245018 September lo,1991 The Honorable John Glenn Chairman, Committee on Governmental Affairs United States Senate The Honorable Brock Adams United States Senate Since 1943 the Washington State Department of Labor and Industries has had a contract with the Department of Ene... |
Date April 18, 1991 |
Report No. T-RCED-91-40 |
Title
United States General Accounting Office / 976 7+ GAO
For Release on Delivery Expected at l:OOp.m. EDT Thursday April 18, 1991 Testimony llllllll IIMl
143674 NUCLEAR WEAPONS COMPLEX Reconfiguring DOE’ Weapons Complex s Statement of J. Dexter Peach AssistantComptroller General Resources,Community, and Economic Development Division
Before the Department of Energy Defense Nuclear Facilities Panel Co... |
Date March 13, 1991 |
Report No. T-RCED-91-21 |
Title
United States General Accounting Office /v 3 772 Testimony Ill II lllll llllll
143472 NUCLEAR MATERIALS GAO’ Views on Decreasing Tritium s Requirements and Their Effect on DOE Programs Statement of Victor S. Rezendes Director, Energy Issues Resources, Community, and Economic Development Division
Before the Department of Energy Defense Nuclear Facilities Panel Committee on Armed Services House of... |
Date March 13, 1991 |
Report No. T-RCED-91-19 |
Title
* I ” United States General Accounting Office /t’ 3360 > GAO
For Reletrse on Deli\wy fipected ot I:30 pm. EST Wednesdrry Murch 13, 1991 Testimony 143360 NUCLEAR WEAPONS COh’ LEX GAO’ Views on DOE’ s s Reconfiguration Study Statement of Victor S. Rezendes Director, Energy Issues Resources, Com m unity, and Econom ic Developm ent Division
Before the Departm ent of Energy Defense Nuclear Fa... |
Date March 1, 1991 |
Report No. RCED-91-66 |
Title
‘ -... .:: :. .I/., .,, ,,_ C:.!. . . ;‘ ,,., Preface -- The nation’ economy, environmental quality, defense, and international s strategy are inextricably linked to the energy choices we make. To assist the Congress in mc>ctingthe challenges associated with these choices, GAOhas long beon an active participant in the debate on major energy questions. Our prc\Gus work has led us to identify ... |