Menu Search Account

LegiStorm

Get LegiStorm App Visit Product Demo Website
» Get LegiStorm App
» Get LegiStorm Pro Free Demo

Major Automated Information Systems: Selected Defense Programs Need to Implement Key Acquisition Practices

  Premium   Download PDF Now (100 pages)
Report Type Reports and Testimonies
Report Date March 27, 2014
Release Date March 27, 2014
Report No. GAO-14-309
Summary:

What GAO Found

Of the 15 selected Department of Defense (DOD) major automated information system (MAIS) programs, 13 had cost information available (2 did not, due to revisions to requirements and changes in scope). Of these 13 programs, 11 experienced changes in their cost estimates, including 7 that experienced increases ranging from 4 to 2,233 percent and 4 that experienced decreases ranging from 4 to 86 percent. Two programs remained unchanged in their cost goals. Additionally, of 14 programs that had schedule information available (1 did not due to revisions to requirements), 13 experienced schedule changes—including 12 that had slippages ranging from a few months to 6 years, and 1 that accelerated its schedule. One program remained on schedule. Further, of 11 programs that had system performance data available, 3 programs met their system performance targets, while 8 did not fully meet their targets.

The three programs selected for analysis of risk management demonstrated mixed progress in effectively defining and managing risks. Specifically, the Defense Health Agency's (DHA) Theater Medical Information Program – Joint Increment 2 had implemented key risk management practices. While the Navy's Global Combat Support System – Marine Corps program did not, among other things, update its risk tracking log during a 5-month period in 2013, the program recently updated its risks and mitigation plans, which should help the program to more effectively manage risks going forward. The Defense Logistics Agency's (DLA) Defense Agencies Initiative program had taken steps to implement selected risk management practices, including establishing a risk management board. However, the program was still in the early stages of identifying risks and had not yet identified a comprehensive set of program risks, nor consistently evaluated and categorized its risks. Until this program maintains a complete risk log and mitigation plans, and accurately evaluates and categorizes its risks, it will lack assurance that it is appropriately mitigating all identified risks.

The three programs also demonstrated mixed progress in implementing key requirements management and project monitoring and control best practices. Specifically, the Navy program had implemented all key requirements management best practices and the DLA program had recently taken steps to do so. However, while the DHA program had implemented many requirements management best practices, it had not maintained complete traceability between its requirements and work products. Additionally, the DHA program had not updated its capabilities baseline to reflect program scope changes. Until DHA implements these requirements management best practices, stakeholders will lack assurance that the system will have all intended functionality to meet users' needs. Regarding project monitoring and control, each of the programs lacked key practices. For instance, the DLA program had not tracked significant deviations in performance. Additionally, the Navy program did not always take timely corrective actions to address issues. Further, the DHA program did not use earned value management to track contractor performance in meeting planned cost targets, even though these data were being collected and certain contracts met DOD's threshold for its use; as such, the program had not effectively determined progress against the plan. Until the three programs implement these project monitoring best practices, they will be limited in their ability to manage the programs.

Why GAO Did This Study

The National Defense Authorization Act for Fiscal Year 2012 mandated that GAO select and assess DOD MAIS programs annually through March 2018. This report discusses the results of GAO's second annual assessment. Based on the act's requirements, GAO's objectives were to (1) describe the extent to which selected MAIS programs have changed their planned cost and schedule estimates and met performance targets; (2) assess selected MAIS programs' actions to manage risks; and (3) assess the extent to which selected MAIS programs used key information technology acquisition best practices.

To do so, GAO selected 15 of the 42 DOD MAIS programs based on several factors, including representation from multiple DOD components, and summarized the results of analyses of cost, schedule, and performance across the programs. Further, GAO selected 3 of the 15 programs (1 each from DHA, DLA, and Navy) and assessed them against best practices for risk management, requirements management, and project monitoring and control.

What GAO Recommends

GAO recommends that DOD direct the programs to address respective weaknesses in their risk management, requirements management, and project monitoring and control practices. DOD concurred with six of GAO's recommendations and partially concurred with the remaining two. GAO maintains that it is important that the DHA program trace all capabilities to their associated requirements and update its capabilities baseline to reflect program scope changes.

For more information, contact Carol R. Cha at (202) 512-4456 or chac@gao.gov.

« Return to search Government Accountability Office reports